Initial checksBuildings & townships · Sirsa, Haryana

Expansion of Grain Based Ethanol Plant From 300 Klpd to 420 Klpd by Modernization in Fermentation Technology and Change in Process Parameter to Achieve Higher Alcohol Production Within the Existing Plant

Expansion of Grain Based Ethanol Plant From 300 Klpd to 420 Klpd by Modernization in Fermentation Technology and Change in Process Parameter to Achieve Higher Alcohol Production Within the Existing Plant is a proposed industrial building project in Haibuwana, Dabwali, Sirsa, Haryana. The site covers 24.7 acres. Its stated project cost is ₹193 crore. As of 27 Nov 2026, its status is “Initial checks” (since 24 Jun 2025).

See it on the live map All projects in Sirsa

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Expansion of Grain Based Ethanol Plant From 300 Klpd to 420 Klpd by Modernization in Fermentation Technology and Change in Process Parameter to Achieve Higher Alcohol Production Within the Existing Plant is a proposed industrial building project in Haibuwana, Dabwali, Sirsa, Haryana. The site covers 24.7 acres.

Who is building it?

The applicant is E20 Greenfuels Private Limited.

Has it been approved?

Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.

Where is it?

In Haibuwana, Dabwali, Sirsa, Haryana.

How big is it?

It has a stated cost of ₹193 crore and a site of 24.7 acres.

When was it filed?

The application was filed on 24 Jun 2025.

One of 2 filings for this project. The project's main page, with every filing and where each stands: Expansion of Grain Based Ethanol Plant From 300 Klpd to 420 Klpd by Modernization in…

Project details

Official titleExpansion of Grain Based Ethanol Plant From 300 Klpd to 420 Klpd by Modernization in Fermentation Technology and Change in Process Parameter to Achieve Higher Alcohol Production Within the Existing Plant at Village Panniwala Ruldu, Tehsil Dabwali, District Sirsa, Haryana by M/S. E20 Greenfuels Private Limited
StatusInitial checks
Status since24 Jun 2025
Application filed24 Jun 2025
Approval soughtEnvironmental approval
Application typeNew project
SectorBuildings & townships
ApplicantE20 Greenfuels Private Limited
UseIndustrial
Land area24.7 acres (10 ha)
Plot area1,00,000 m² (10,76,390 sq ft)
Project cost₹193 crore
Village / localityHaibuwana
Taluk / tehsilDabwali
DistrictSirsa
StateHaryana
Location fromSite boundary on record
Our referenceWID-HR-00720

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 4 Jul 2025Initial checks24.7 acres₹193 crore
New project filed 24 Jun 2025 (this page)Initial checks24.7 acres₹193 crore

In context

80 applications in Sirsa since January 2022 are in the same category (Buildings & townships): 17 approved, 14 filed or under review, and 49 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 24.7 acres, this one is larger than 95% of them.

7 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Haibuwana, Dabwali, Sirsa, Haryana. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from E20 Greenfuels Private Limited in Sirsa

All 5 E20 Greenfuels projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.