Quick answers
What is this project?
Expansion of existing Sponge Iron plant from 54,000 TPA to 174,000 TPA, Installation of 3 x 20 Ton Induction Furnaces with Billet Caster for production of 174,000 TPA Rolled Products is an approved industrial project in Bokaro Steel City, Chas, Bokaro, Jharkhand. The site covers 25 acres.
Who is building it?
The applicant is Sundaram Steels Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 18 Jan 2023), as of 27 Nov 2026.
Where is it?
In Bokaro Steel City, Chas, Bokaro, Jharkhand.
How big is it?
It has a stated cost of ₹2.2 crore and a site of 25 acres.
When was it filed?
The application was filed on 18 Jan 2023.
Project details
| Official title | Expansion of existing Sponge Iron plant from 54,000 TPA to 174,000 TPA, Installation of 3 x 20 Ton Induction Furnaces with Billet Caster for production of 174,000 TPA Rolled Products along with 24 MW Captive Power Plant by M/s Sundaram Steels Private Limited at B-7, Phase-III, Bokaro Industrial Area, Balidih, Bokaro, Jharkhand. |
|---|---|
| Status | Environmental approval granted |
| Status since | 18 Jan 2023 |
| Application filed | 18 Jan 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Sundaram Steels Private Limited |
| Land area | 25 acres (10.1 ha) |
| Project cost | ₹2.2 crore |
| Village / locality | Bokaro Steel City |
| Taluk / tehsil | Chas |
| District | Bokaro |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-00421 |
In context
27 applications in Bokaro since January 2022 are in the same category (Industry): 16 approved, 4 filed or under review, and 7 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 25 acres, this one is larger than 70% of them.
25 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bokaro Steel City, Chas, Bokaro, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Initimation regarding change in Type of Boiler from AFBC to CFBC under "No… — initial checks, 0 m away
- Expansion of Existing plant for total production of 0.6864 MTPA Sponge Iron,… — withdrawn, 100 m away
- Expansion of Existing plant for total production of 0.6864 MTPA Sponge Iron,… — cleared for impact study, 100 m away
- ENVIRONMENTAL CLEARANCE TO ENHANCE THE PRODUCTION OF M.S INGOT/BILLET FROM… — lapsed, 350 m away
- Industrial project by Bokaro Spirits & Allied Industries Private Limited — environmental approval granted, 550 m away
- Transfer of Environment Clearance and its Corrigendum in EC from Castron… — lapsed, 1 km away
- Greenfield Ferro Alloys Plant for production of 40,000 TPA (Max.) Ferro Alloys… — cleared for impact study, 1.1 km away
- Greenfield Ferro Alloys Plant for production of 31,000 TPA (max.) Ferro Alloys… — environmental approval granted, 1.3 km away
More from Sundaram Steels Private Limited in Bokaro
- Expansion of Existing plant for total production of 0.6864 MTPA Sponge Iron,… — cleared for impact study
- Expansion of Existing plant for total production of 0.6864 MTPA Sponge Iron,… — withdrawn
- Initimation regarding change in Type of Boiler from AFBC to CFBC under "No… — initial checks
All 4 Sundaram Steels projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.