What is Developing? Open the mapMap

Initial checksBuildings & townships · Saraikela-Kharsawan, Jharkhand

Change in the raw material mix by replacement of Domestic Scrap with Imported Scrap for production of 2,21,760 TPA Billets in the existing SMS plant within approved EC capacity by Amalgam Steel & Power Ltd

Change in the raw material mix by replacement of Domestic Scrap with Imported Scrap for production of 2,21,760 TPA Billets in the existing SMS plant within approved EC capacity by Amalgam Steel & Power Ltd is a proposed industrial building project in Bankipur, Adityapur(Gamharia), Saraikela-Kharsawan, Jharkhand. The site covers 80.3 acres. Its stated project cost is ₹554 crore. As of 27 Nov 2026, its status is “Initial checks” (since 23 Apr 2025).

See it on the live map All projects in Saraikela-Kharsawan

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Change in the raw material mix by replacement of Domestic Scrap with Imported Scrap for production of 2,21,760 TPA Billets in the existing SMS plant within approved EC capacity by Amalgam Steel & Power Ltd is a proposed industrial building project in Bankipur, Adityapur(Gamharia), Saraikela-Kharsawan, Jharkhand. The site covers 80.3 acres.

Who is building it?

The applicant is Amalgam Steel & Power Limited.

Has it been approved?

Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.

Where is it?

In Bankipur, Adityapur(Gamharia), Saraikela-Kharsawan, Jharkhand.

How big is it?

It has a stated cost of ₹554 crore and a site of 80.3 acres.

When was it filed?

The application was filed on 23 Apr 2025.

Project details

Official titleChange in the raw material mix by replacement of Domestic Scrap with Imported Scrap for production of 2,21,760 TPA Billets in the existing SMS plant within approved EC capacity by Amalgam Steel & Power Ltd. at Village Kandra, Tilopada, Bankipur and Raimara in Gamharia Block, District Saraikela-Kharsawan, Jharkhand
StatusInitial checks
Status since23 Apr 2025
Application filed23 Apr 2025
Approval soughtEnvironmental approval
Application typeNew project
SectorBuildings & townships
ApplicantAmalgam Steel & Power Limited
UseIndustrial
Height30 m
Land area80.3 acres (32.5 ha)
Project cost₹554 crore
Village / localityBankipur
Taluk / tehsilAdityapur(Gamharia)
DistrictSaraikela-Kharsawan
StateJharkhand
Location fromSite boundary on record
Our referenceWID-JH-01818

In context

20 applications in Saraikela-Kharsawan since January 2022 are in the same category (Buildings & townships): 15 approved, 2 filed or under review, and 3 withdrawn, lapsed or rejected. The approved ones took a median of 43 days from filing to approval. At 80.3 acres, this one is larger than 95% of them.

12 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Bankipur, Adityapur(Gamharia), Saraikela-Kharsawan, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.