Proposed Modernization cum Expansion of Integrated Steel Plant with Sponge Iron (DRI) 0.231 MTPA to 0.561 MTPA, Steel Billets (MS Billets) 0.198 MTPA to 0.435 MTPA, Rolling Mill (MS Bars & Structural Steel) 0.192 MTPA to 0.425 MTPA with Iron Ore crusher 0.841 MTPA, Ferro alloys 0.148 MTPA, Slag Crusher 0.198 MTPA and Captive Power Plant 30 MW to 110 MW with Increase in Land area from 27.34 ha to 30.45 ha by M/s Krishna Sponge Iron and Power Private Limited

Proposed Modernization cum Expansion of Integrated Steel Plant with Sponge Iron (DRI) 0.231 MTPA to 0.561 MTPA, Steel Billets (MS Billets) 0.198 MTPA to 0.435 MTPA, Rolling Mill (MS Bars & Structural Steel) 0.192 MTPA to 0.425 MTPA with Iron Ore crusher 0.841 MTPA, Ferro alloys 0.148 MTPA, Slag Crusher 0.198 MTPA and Captive Power Plant 30 MW to 110 MW with Increase in Land area from 27.34 ha to 30.45 ha by M/s Krishna Sponge Iron and Power Private Limited is a proposed industrial project in Kamalpur, Saraikela, Saraikela-Kharsawan, Jharkhand. The site covers 75.2 acres. Its stated project cost is ₹2,126 crore. As of 27 Nov 2026, its status is “Under environmental review” (since 26 Nov 2026).

See it on the live map All projects in Saraikela-Kharsawan

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Proposed Modernization cum Expansion of Integrated Steel Plant with Sponge Iron (DRI) 0.231 MTPA to 0.561 MTPA, Steel Billets (MS Billets) 0.198 MTPA to 0.435 MTPA, Rolling Mill (MS Bars & Structural Steel) 0.192 MTPA to 0.425 MTPA with Iron Ore crusher 0.841 MTPA, Ferro alloys 0.148 MTPA, Slag Crusher 0.198 MTPA and Captive Power Plant 30 MW to 110 MW with Increase in Land area from 27.34 ha to 30.45 ha by M/s Krishna Sponge Iron and Power Private Limited is a proposed industrial project in Kamalpur, Saraikela, Saraikela-Kharsawan, Jharkhand. The site covers 75.2 acres.

Who is building it?

The applicant is Krishna Sponge Iron and Power Private Limited.

Has it been approved?

Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.

Where is it?

In Kamalpur, Saraikela, Saraikela-Kharsawan, Jharkhand.

How big is it?

It has a stated cost of ₹2,126 crore and a site of 75.2 acres.

When was it filed?

The application was filed on 19 Nov 2026.

Project details

StatusUnder environmental review
Status since26 Nov 2026
Application filed19 Nov 2026
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantKrishna Sponge Iron and Power Private Limited
Land area75.2 acres (30.5 ha)
Project cost₹2,126 crore
Village / localityKamalpur
Taluk / tehsilSaraikela
DistrictSaraikela-Kharsawan
StateJharkhand
Location fromSite boundary on record
Our referenceWID-JH-02723

In context

47 applications in Saraikela-Kharsawan since January 2022 are in the same category (Industry): 24 approved, 11 filed or under review, and 12 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 75.2 acres, this one is larger than 68% of them.

9 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Kamalpur, Saraikela, Saraikela-Kharsawan, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Krishna Sponge Iron and Power Private Limited in Saraikela-Kharsawan

All 3 Krishna Sponge Iron projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.