Quick answers
What is this project?
125 KLPD Grain based Distillery by Sarvabhouma Sugars Pvt. Ltd is a lapsed industrial project in Chattarki, Sindgi, Vijayapura, Karnataka. The site covers 38.2 acres.
Who is building it?
The applicant is Sarvabhouma Sugars Private Limited.
Has it been approved?
No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.
Where is it?
In Chattarki, Sindgi, Vijayapura, Karnataka.
How big is it?
It has a stated cost of ₹150 crore and a site of 38.2 acres.
When was it filed?
The application was filed on 30 Mar 2024.
Project details
| Official title | Establishment of 125 KLPD Grain based Distillery along with 2 MW Electricity Generation by Sarvabhouma Sugars Pvt. Ltd. |
|---|---|
| Status | Lapsed |
| Status since | 29 Oct 2024 |
| Application filed | 30 Mar 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Sarvabhouma Sugars Private Limited |
| Land area | 38.2 acres (15.4 ha) |
| Project cost | ₹150 crore |
| Village / locality | Chattarki |
| Taluk / tehsil | Sindgi |
| District | Vijayapura |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-02038 |
In context
37 applications in Vijayapura since January 2022 are in the same category (Industry): 20 approved, 8 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 38.2 acres, this one is smaller than 84% of them.
Where it is
Chattarki, Sindgi, Vijayapura, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- "Building Stone Quarry" of Sri. Hobu S/o Shankar Pawar — environmental approval granted, 11.2 km away
- "Building Stone Quarry" of Sri. Bhimaraya T Sunagar — environmental approval granted, 13.3 km away
- "Building Stone Quarry" of M/s. S.S. Alur Construction Company, — environmental approval granted, 14.6 km away
- Proposed 8000TCD Sugar Plant and 25 MW Co- generation Power plant and 200 KLPD… — cleared for impact study, 15.2 km away
- Shivanagi Building Stone Quarry — environmental approval granted, 17.1 km away
- Expansion of Sugar and Co-Generation Unit and Establishment of Distillery Unit… — environmental approval granted, 19.6 km away
- Amendment to the Environmental Clearance Issued for Expanding the Sugar Plant,… — environmental approval granted, 20.7 km away
- Expansion of Sugar Plant From 3500 Tcd to 7500 Tcd, Co-Generation Power Plant… — lapsed, 20.7 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.