Quick answers
What is Jakkasandra Industrial Area Phase-II (Mindahalli)?
Jakkasandra Industrial Area Phase-II (Mindahalli) is an approved industrial project in Jakksandra, Malur, Kolar, Karnataka. The site covers 335.4 acres.
Who is building it?
The applicant is Karnataka Industrial Areas Development Board.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 10 Feb 2025), as of 27 Nov 2026.
Where is it?
In Jakksandra, Malur, Kolar, Karnataka.
How big is it?
It has a stated cost of ₹548.8 crore and a site of 335.4 acres.
When was it filed?
The application was filed on 19 Dec 2024.
Project details
| Official title | Proposed Development of Jakkasandra Industrial Area Phase-II (Mindahalli) |
|---|---|
| Status | Environmental approval granted |
| Status since | 10 Feb 2025 |
| Application filed | 19 Dec 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Karnataka Industrial Areas Development Board |
| Land area | 335.4 acres (135.7 ha) |
| Project cost | ₹548.8 crore |
| Village / locality | Jakksandra |
| Taluk / tehsil | Malur |
| District | Kolar |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-02039 |
What the filings say
What is planned
The applicant's project report says the Jakkasandra Industrial Area Phase-II will be developed to host Category B and non-EC industries. Out of the total 135.74 hectares (335.41 acres), 88.18 hectares (217.90 acres) are allotted for industrial plots and 2.47 hectares (6.10 acres) for commercial activities. The remaining land is earmarked for utilities, roads, parking, and a green belt. The estate is planned to accommodate various sectors, including engineering, plastics, food and dairy products, textiles, and warehousing. The project is expected to employ 75 people during construction and 6,500 people once fully operational.
Water, power and access
The industrial area will require 16 MVA of power, which will be sourced from the Karnataka Power Transmission Corporation Limited (KPTCL). The total water requirement during the operation phase is estimated at 1,847 kilolitres per day (KLD). This includes 440 KLD of fresh water, which will be supplied using tertiary treated water from the Narsapura plant owned by KIADB, and 1,084 KLD of recycled water. Domestic water needs will be met through borewells.
Environmental safeguards
The applicant proposes a Zero Liquid Discharge (ZLD) system for the industrial area. Sewage generation is estimated at 268 KLD, which will be treated in a 350 KLD Common Sewage Treatment Plant (CSTP). Industrial effluent of 819 KLD will be treated in a 1,100 KLD Common Effluent Treatment Plant (CETP). The treated water will be reused for utilities, industrial processes, and green belt development.
Solid waste will be segregated at the source; organic waste will be composted on-site, while inorganic waste will be sold to authorised recyclers. The project includes the construction of 171 rainwater harvesting pits. A green belt is planned over 44.79 hectares (110.68 acres), covering 33% of the developable area, where 1,12,000 trees of native species will be planted.
What was said at the public hearing
A public hearing was held on 19 July 2023 at the project site. Residents from Mindahalli and nearby villages raised concerns about land compensation, the need for a 100-metre buffer between the industrial area and the village, road connections, and solid waste disposal. They also requested land for a cremation ground next to the local lake.
In response, KIADB officials stated that a 16.87-hectare buffer area is already earmarked in the layout, which can be utilised for cremation by the villagers. They assured that land compensation is being processed as per norms and that ₹8.25 crore is allocated for Corporate Environmental Responsibility (CER) activities to develop basic facilities in Jakkasandra and nearby villages.
Timeline
The Terms of Reference (ToR) for the environmental study were issued in December 2022. Following the public hearing in July 2023 and the submission of the final Environmental Impact Assessment (EIA) report in March 2024, the project was granted environmental approval in February 2025.
Jakkasandra Industrial Area Phase-II (Mindahalli) site plan and layout
A drawing from the project's filings. Sign in free to see it.
🔒 Sign in free to see itIn context
14 applications in Kolar since January 2022 are in the same category (Industry): 10 approved, 2 filed or under review, and 2 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 335.4 acres, this one is larger than 57% of them.
38 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Jakksandra, Malur, Kolar, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed "Warehousing, Industrial and Logistics Park" project by M/s. ILV… — under environmental review, 650 m away
- "Factory -E, EV Two Wheeler & Parts" by M/s. Honda Motorcycle and Scooter… — under environmental review, 1.2 km away
- River EV 2 Wheelers Assembling Facility — initial checks, 1.5 km away
- Expansion of Industrial and Logistic Park by M/S. Deerfield Logistics Private… — more information requested, 1.5 km away
- Industrial and Warehouse Building by M/s. IndoSpace Park Narsapura II Private… — environmental approval granted, 1.9 km away
- Proposed Industrial and Warehouse Building project by M/s. Sunlarge Developers… — environmental approval granted, 1.9 km away
- Proposed Industrial and Warehouse Building project by M/s. Sunlarge Developers… — environmental approval granted, 1.9 km away
- Industrial project by APL Apollo Tubes Limited — lapsed, 1.9 km away
More from Karnataka Industrial Areas Development Board in Kolar
- K.G.F Industrial Area located at Sy.No 2, Bangaradagani Village, K.G.F Taluk,… — cleared for impact study
- Diversion of 0.2241 ha (0.2240899 ha) of forest land in Sy No.1 of Hale… — lapsed
- Design and construction of Working women's Hostel buildings — environmental approval granted
8 Karnataka Industrial Areas Development Board projects in Kolar
All 109 Karnataka Industrial Areas Development Board projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.