What is this project?
Cement manufacturing with Clinker Plant for 1.0 MTPA & Cement Plant for 3.0 MTPA, over an area of 79.71 Acre (32.26 Ha.) in MIDC Plot No. A-27 & A-28 at Tadali Growth Centre, Chandrapur, Maharashtra by M/s. OSR Cement Private Limited is a proposed industrial project in Yerur, Chandrapur, Maharashtra. The site covers 79.7 acres.
Who is building it?
The applicant is Osr Cement Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 24 Jun 2024), as of 27 Nov 2026.
Where is it?
In Yerur, Chandrapur, Maharashtra.
How big is it?
It has a stated cost of ₹369 crore and a site of 79.7 acres.
When was it filed?
The application was filed on 19 Jun 2024.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 24 Jun 2024 |
| Application filed | 19 Jun 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Osr Cement Private Limited |
| Land area | 79.7 acres (32.3 ha) |
| Project cost | ₹369 crore |
| Village / locality | Yerur |
| Taluk / tehsil | Chandrapur |
| District | Chandrapur |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-04912 |
In context
55 applications in Chandrapur since January 2022 are in the same category (Industry): 38 approved, 11 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 79.7 acres, this one is smaller than 71% of them.
14 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Yerur, Chandrapur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Expansion of Sponge Iron Plant from 1,87,500 TPA (2 x 100 TPD and 1 x… — initial checks, 550 m away
- Name change of M/s. Grace Industries Ltd. for Expansion of Existing Steel… — withdrawn, 1.7 km away
- Name Change of M/s. Grace Industries Ltd. at Plot No. A-23, A-24, A-25,… — withdrawn, 1.7 km away
- Expansion of Existing Steel Plant with Iron Ore Beneficiation (3.36 MTPA),… — environmental approval granted, 1.7 km away
- Expansion of Existing Steel Plant with Iron Ore Beneficiation (3.36 MTPA),… — lapsed, 1.7 km away
- Grain Base fuel ethanol unit of 200 KLD, 5.5 MW Co- generation power plant By… — lapsed, 2.7 km away
- "Proposed Expansion of manufacturing plant with Sponge Iron from 90,000 TPA to… — cleared for impact study, 2.7 km away
- Grain Base fuel ethanol unit of 200 KLD, 5.5 MW Co- generation power plant By… — environmental approval granted, 2.7 km away