Quick answers
What is this project?
Transfer of Environment Clearance letter issued by SEIAA Maharashtra, Mumbai from M/s Shree Sidhbali Ispat Ltd. to M/s OMAT West Limited for Proposed Expansion of Steel Melting Shop & Setting up of 1 x 20 MW Captive Power Plant within existing set up of Minin Integrated Steel Plant in MIDC Area at C-2 & C-3, MIDC, Chandrapur Growth Center, Tadali, Tehsil & District: Chandrapur, State: Maharashtra is an approved industrial project in Reserved Forest, Chandrapur, Maharashtra. The site covers 103.2 acres.
Who is building it?
The applicant is OMAT West Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 9 Apr 2025), as of 27 Nov 2026.
Where is it?
In Reserved Forest, Chandrapur, Maharashtra.
How big is it?
It has a stated cost of ₹125 crore and a site of 103.2 acres.
When was it filed?
The application was filed on 30 Aug 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 9 Apr 2025 |
| Application filed | 30 Aug 2024 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Industry |
| Applicant | OMAT West Limited |
| Land area | 103.2 acres (41.8 ha) |
| Project cost | ₹125 crore |
| Village / locality | Reserved Forest |
| Taluk / tehsil | Chandrapur |
| District | Chandrapur |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-05918 |
In context
55 applications in Chandrapur since January 2022 are in the same category (Industry): 38 approved, 11 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 103.2 acres, this one is smaller than 65% of them.
14 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Reserved Forest, Chandrapur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- "Proposed Expansion of manufacturing plant with Sponge Iron from 90,000 TPA to… — cleared for impact study, 0 m away
- Expansion of Steel Melting Shop & Setting up of 1 x 20 MW Captive Power Plant… — environmental approval granted, 0 m away
- "Proposed Expansion of manufacturing plant with Sponge Iron from 90,000 TPA to… — withdrawn, 0 m away
- "Proposed Expansion of manufacturing plant with Sponge Iron from 90,000 TPA to… — cleared for impact study, 0 m away
- "Proposed Expansion of manufacturing plant with Sponge Iron from 90,000 TPA to… — cleared for impact study, 50 m away
- Amendment in Environmental Clearance for seeking review of applicability of… — environmental approval granted, 800 m away
- Grain Base fuel ethanol unit of 200 KLD, 5.5 MW Co- generation power plant By… — environmental approval granted, 1.6 km away
- Grain Base fuel ethanol unit of 200 KLD, 5.5 MW Co- generation power plant By… — lapsed, 1.6 km away
More from OMAT West Limited in Chandrapur
- "Proposed Expansion of manufacturing plant with Sponge Iron from 90,000 TPA to… — cleared for impact study
- Expansion of Steel Melting Shop & Setting up of 1 x 20 MW Captive Power Plant… — environmental approval granted
- "Proposed Expansion of manufacturing plant with Sponge Iron from 90,000 TPA to… — withdrawn
- "Proposed Expansion of manufacturing plant with Sponge Iron from 90,000 TPA to… — cleared for impact study
All 5 Omat West projects across India