What is this project?
Proposed Project by M/s. Sangam Solar One Private Limited at Plot No-E6, MIDC Butibori Industrial Area, Nagpur, Maharashtra is a proposed industrial building project in Bori, Nagpur (Rural), Nagpur, Maharashtra. The site covers 300 acres.
Who is building it?
The applicant is Sangam Solar One Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Bori, Nagpur (Rural), Nagpur, Maharashtra.
How big is it?
It has a stated cost of ₹5,800 crore and a site of 300 acres.
When was it filed?
The application was filed on 3 Jul 2026.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 21 Sept 2026 |
| Application filed | 3 Jul 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Buildings & townships |
| Applicant | Sangam Solar One Private Limited |
| Use | Industrial |
| Land area | 300 acres (121.4 ha) |
| Project cost | ₹5,800 crore |
| Village / locality | Bori |
| Taluk / tehsil | Nagpur (Rural) |
| District | Nagpur |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-12500 |
In context
168 applications in Nagpur since January 2022 are in the same category (Buildings & townships): 128 approved, 22 filed or under review, and 18 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 300 acres, this one is larger than 97% of them.
28 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bori, Nagpur (Rural), Nagpur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Ingot & Wafer Manufacturing 6 GW Plant by Sangam Solar One Private Limited at… — environmental approval granted, 0 m away
- Addl. Butibori Industrial Area (Village -Dhawalpeth Survey No 70) — under forest review, 350 m away
- 1200 MTPD Solar Glass plant by M/s. Avaada Glass Pvt. Ltd., at Plot No.… — environmental approval granted, 1.5 km away
- 1200 MTPD Solar Glass plant by M/s. Avaada Glass Pvt. Ltd., at Plot No.… — cleared for impact study, 1.5 km away
- Diversion of 21.08 Ha. of forest department (Zudpi Jungle) land for Additional… — lapsed, 1.7 km away
- Expansion in Proposed installation of Integrated 6 GW cell and 5GW module line… — environmental approval granted, 1.8 km away
- Expansion in Proposed installation of Integrated 6 GW cell and 5GW module line… — initial checks, 1.8 km away
- Expansion in Proposed installation of Integrated 6 GW cell and 5GW module line… — environmental approval granted, 1.8 km away
More from Sangam Solar One Private Limited in Nagpur
- Ingot & Wafer Manufacturing 6 GW Plant by Sangam Solar One Private Limited at… — environmental approval granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.