What is this project?
Expansion and Modification of an existing plant facilities (62,700 TPA DRI to 92,400 TPA DRI, 4MW WHRB to 5 MW WHRB), 2X4.5 MTPA Iron Ore Grinding Unit, 10.0 MTPA Thickening & Filtration Unit and 2X4.0 MTPA Iron Ore Pellet Plant by setting an additional Integrated Steel Plant (ISP) of 4.5 MTPA Capacity with 483 MW (488MW total) Captive Power Plant and 5.0 MTPA Filtration Unit at Plot No. A-1, MIDC Konsari, Survey No. 174, 198 and Others by Lloyds Metals & Energy Limited is a proposed power project in Konsari, Chamorshi, Gadchiroli, Maharashtra. The site covers 1,304.6 acres.
Who is building it?
The applicant is M/S. Lloyds Metals and Energy Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Konsari, Chamorshi, Gadchiroli, Maharashtra.
How big is it?
It has a stated cost of ₹24,470 crore and a site of 1,304.6 acres.
When was it filed?
The application was filed on 11 Sept 2026.
One of 3 filings for this project. The project's main page, with every filing and where each stands: Expansion and Modification of an existing plant facilities (62,700 TPA DRI to 92,400 TPA…
Project details
| Status | Initial checks |
|---|---|
| Status since | 11 Sept 2026 |
| Application filed | 11 Sept 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Power |
| Applicant | M/S. Lloyds Metals and Energy Limited |
| Land area | 1,304.6 acres (528 ha) |
| Project cost | ₹24,470 crore |
| Village / locality | Konsari |
| Taluk / tehsil | Chamorshi |
| District | Gadchiroli |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-13937 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 11 Sept 2026 (this page) | Initial checks | 1,304.6 acres | ₹24,470 crore |
| Expansion filed 13 Jun 2025 | Environmental approval granted | 1,304.6 acres | ₹24,470 crore |
| Early planning filed 9 Aug 2024 | Cleared for impact study | 1,304.6 acres | ₹24,470 crore |
In context
5 applications in Gadchiroli since January 2022 are in the same category (Power): 0 approved, 4 filed or under review, and 1 withdrawn, lapsed or rejected.
9 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Konsari, Chamorshi, Gadchiroli, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed expansion by Thickening & Filtration Unit from 10 to 10.6 MTPA &… — under environmental review, 0 m away
- Expansion and Modification of an existing plant facilities (62,700 TPA DRI to… — environmental approval granted, 0 m away
- Expansion and Modification of an existing plant facilities (62,700 TPA DRI to… — cleared for impact study, 0 m away
- Forest Diversion Proposal Over 39.864 Ha of Forest Land for Optimum and… — more information requested, 750 m away
- Expansion of Project by Installation of 2 x 4.5 MTPA Iron Ore Grinding Unit,… — environmental approval granted, 950 m away
- Expansion of Project by Installation of 2 x 4.5 MTPA Iron Ore Grinding Unit,… — environmental approval granted, 950 m away
- Expansion of Project by Installation of 2 x 4.5 MTPA Iron Ore Grinding Unit,… — cleared for impact study, 950 m away
- Proposed Diversion of Forest Land Over 13.726 Ha for Proposed Railway Line and… — not approved, 2.5 km away
More from M/S. Lloyds Metals and Energy Limited in Gadchiroli
- Expansion of Project by Installation of 2 x 4.5 MTPA Iron Ore Grinding Unit,… — environmental approval granted
- Proposed Greenfield 3.0 MTPA Integrated Steel Plant (1x1.5 MTPA Coke Oven… — cleared for impact study
- Expansion of Project by Installation of 2 x 4.5 MTPA Iron Ore Grinding Unit,… — environmental approval granted
- Expansion of Project by Installation of 2 x 4.5 MTPA Iron Ore Grinding Unit,… — cleared for impact study
29 Lloyds Metals and Energy projects in Gadchiroli
All 40 Lloyds Metals and Energy projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.