Project details
| Official title | RE-DIVERSION OF 0.9988 HA. FOREST LAND FOR SHIFTING OF EXISTING 220kV BOISAR -BORIVALI & BOISAR -GHODBUNDAR M/C LINE LOC. NO.209 - 210 AGAINST THE INFRINGEMENT CROSSING WITH M/S NHSRCL PROPOSED ALIGNMENTS AT KAMAN VILLAGE, TAL-VASAI PASSING THROUGH PALGHAR DISTRICT STATE OF MAHARASHTRA. |
|---|---|
| Status | In-principle approval, conditions pending |
| Status since | 2 Oct 2024 |
| Application filed | 27 May 2024 |
| Approval sought | Forest land use |
| Application type | Change of use |
| Sector | Buildings & townships |
| Applicant | Mahatransco |
| Use | Other |
| Land area | 7.6 acres (3.1 ha) |
| Forest land | 2.5 acres (1 ha) |
| Plot area | 9,988 m² (1,07,510 sq ft) |
| Project cost | ₹26.3 crore |
| Village / locality | Kaman |
| Taluk / tehsil | Vasai |
| District | Palghar |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-15435 |
In context
250 applications in Palghar since January 2022 are in the same category (Buildings & townships): 152 approved, 49 filed or under review, and 49 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 7.6 acres, this one is larger than 65% of them.
24 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kaman, Vasai, Palghar, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Shifting of Existing 220 Kv Boisar -Borivali & Boisar -Ghodbundar M/C Line,… — in-principle approval, conditions pending, 0 m away
- Proposed School Building of M/s Vidya Vikas education Trust's Universal… — environmental approval granted, 1.4 km away
- Proposed School Building of M/s Vidya Vikas education Trust's Universal… — environmental approval granted, 1.4 km away
- Proposed School Building of M/s Vidya Vikas education Trust's Universal… — environmental approval granted, 1.4 km away
- Proposed Warehouse (Non-polluting) outside CRZ area on land bearing S. No.… — recommended by coastal authority, 1.7 km away
- CRZ Clearance for Proposed Industrial Layout on plot bearing Survey Nos.… — recommended by coastal authority, 2.2 km away
- Building project by M/s Shantee Realtor — environmental approval granted, 2.4 km away
- Diversion of 0.0985 Ha. Reserved Forest Land for "laying the Proposed Railway… — more information requested, 3.5 km away
More from Mahatransco in Palghar
- Diversion of 1.7080 Ha. Forest Land for Proposed Construction 220 KV PG-Manor… — more information requested
- "Lilo on Existing 220kv Boisar (PGCIL) – Vasai Line at 220kv Chikhaldongri… — under forest review
- Diversion of 2.2950 Ha. Forest Land for Proposed 132 KV DCMC line from LILO on… — in-principle approval, conditions pending
- Diversion of 3.9069 Ha Forest Land For Proposed LILO on 132 KV Dahanu –… — in-principle approval, conditions pending
- LILO on existing 220 kV Boisar (PGCIL)-Vasai Line at 220 kV Chikhaldongari… — coastal clearance granted
- 132KV DAHANU-AMBESARI TRANSMISSION LINE FOR ESTABLISHMENT OF PROPOSED NHSRCL'S… — coastal clearance granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.