Quick answers
What is this project?
Construction of New 33/11 KV substation Mohata village Mohata is an approved power project in Mohta, Bhainsdehi, Betul, Madhya Pradesh. The site covers 1.6 acres.
Who is building it?
The applicant is Madhya Pradesh Madhya Kshetra Vidut Vitaran Company Limited.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 5 May 2026), as of 27 Nov 2026.
Where is it?
In Mohta, Bhainsdehi, Betul, Madhya Pradesh.
How big is it?
It has a stated cost of ₹23 lakh; a site of 1.6 acres and 3,000 m² of forest land.
When was it filed?
The application was filed on 2 Jan 2023.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 5 May 2026 |
| Application filed | 2 Jan 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Madhya Pradesh Madhya Kshetra Vidut Vitaran Company Limited |
| Land area | 1.6 acres (0.6 ha) |
| Forest land | 3,000 m² |
| Project cost | ₹23 lakh |
| Village / locality | Mohta |
| Taluk / tehsil | Bhainsdehi |
| District | Betul |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-09622 |
In context
39 applications in Betul since January 2022 are in the same category (Power): 7 approved, 26 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 11 months from filing to approval. At 1.6 acres, this one is smaller than 87% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mohta, Bhainsdehi, Betul, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 11 KV Kamod Mix Feeder, FSP Works under RDSS KfW(FSP) package — more information requested, 3.6 km away
- 11 KV Damjipura Mix Feeder, FSP Works under RDSS KfW(FSP) package — forest land use approved, 5.3 km away
- 11 KV Deshli Mix Feeder, FSP Works under RDSS KfW(FSP) package — under forest review, 9.5 km away
- 4g Saturation Project Under 500 Days — lapsed, 11.9 km away
- Bsnl 4g Saturation Project — lapsed, 11.9 km away
- Bsnl 4g Saturation Project — lapsed, 12 km away
- Two laning of Hiwarkhedi-Basinda- Roshni Section of NH-347B (Old SH-26) from… — decision issued, 13.3 km away
- Two laning of Patajan-Basina- Roshni Section of NH-347B (Old SH-26) from Betul… — lapsed, 13.6 km away
More from Madhya Pradesh Madhya Kshetra Vidut Vitaran Company Limited in Betul
- Electrification of Un-Electrified Villages Utari & Palanga and its habitations… — more information requested
- New 11 KV Kukru DLF Feeder, FSP Works under RDSS KfW(FSP) package — under forest review
- New 11 KV Baramacha DLF Feeder, FSP Works under RDSS KfW(FSP) package — under forest review
- New 11 KV Kharwar DLF Feeder, FSP Works under RDSS KfW(FSP) package — more information requested
- New 11 KV Timarni DLF Feeder, FSP Works under RDSS KfW(FSP) package — under forest review
- New 11 KV Chikhlajodi DLF Feeder, FSP Works under RDSS KfW(FSP) package — under forest review
29 Madhya Pradesh Madhya projects in Betul
All 52 Madhya Pradesh Madhya projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.