| Status | Forest land use approved |
|---|---|
| Status since | 4 May 2026 |
| Application filed | 17 May 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Power Grid Corporation of India (POWERGRID) |
| Land area | 957.9 acres (387.6 ha) |
| Forest land | 400.4 acres (162.1 ha) |
| Project cost | ₹435.3 crore |
| Village / locality | Besli |
| Taluk / tehsil | Banda |
| District | Sagar |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-11195 |
In context
13 applications in Sagar since January 2022 are in the same category (Power): 5 approved, 2 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 17 months from filing to approval. At 957.9 acres, this one is larger than 67% of them.
7 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Besli, Banda, Sagar, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Malthon Multi Village Rural Water Supply Scheme. — lapsed, 1.2 km away
- Malthon Multi Village Drinking Water Supply Scheme — lapsed, 1.2 km away
- Malthon Multi Village Rural Water Supply Scheme Piu Sagar — forest land use approved, 2 km away
- Malthon Multi Village Rural Water Supply Scheme — lapsed, 2 km away
- Shifting of 765KV Jabalpur Bina Transmission Line in Sagar — forest land use approved, 2.6 km away
- Construction of Play Ground in Paharguwa Bandri District Sagar M.P. — lapsed, 3.9 km away
- Construction of Play Ground in Paharguwa Bandri District Sagar — more information requested, 3.9 km away
- Jajer Raiyatwari Flag Stone Quarry — environmental approval granted, 5.4 km away
More from Power Grid Corporation of India (POWERGRID) in Sagar
- Shifting of 400 KV D/c Damoh-Bhopal Transmission Line due to Jera Medium… — under forest review
- Shifting of 400 KV D/c Damoh-Bhopal Transmission Line due to Jera Medium… — lapsed
3 Power Grid Corporation of India projects in Sagar
All 45 Power Grid Corporation of India projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.