What is Developing? Open the mapMap

Not approvedBuildings & townships · Cuttack, Odisha

Proposed 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power Plant by Orissa Thermal Energy Private Limited

Proposed 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power Plant by Orissa Thermal Energy Private Limited is a rejected building project in Rahangol, Khuntuni, Cuttack, Odisha. The site covers 819.1 acres. Its stated project cost is ₹27,438 crore. As of 27 Nov 2026, its status is “Not approved” (since 14 Nov 2025).

See it on the live map All projects in Cuttack

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

Official titleProposed 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power Plant at Village Rahangol, Kandarei, Tehsil Athagarh, District Cuttack, Odisha by Orissa Thermal Energy Private Limited
StatusNot approved
Status since14 Nov 2025
Application filed8 Oct 2025
Approval soughtForest land use
Application typeNew project
SectorBuildings & townships
ApplicantAdani Power Limited
Land area819.1 acres (331.5 ha)
Forest land39.5 acres (16 ha)
Project cost₹27,438 crore
Village / localityRahangol
Taluk / tehsilKhuntuni
DistrictCuttack
StateOdisha
Location fromSite boundary on record
Our referenceWID-OR-04537

What the filings say

What is planned

Adani Power Limited proposes the Nilanchal Thermal Power Plant, a 2,400 MW coal-based facility using ultra-supercritical technology. The project consists of three units, each with a capacity of 800 MW. The applicant's project report indicates the plant will be located across several villages including Rahangol, Kandarei, Dalua, Khanduali, Khuntuni, and Rampei in the Athagarh Tehsil of Cuttack district.

The project components include:

Layout and design

The site layout shows the main power block centrally located, with the ash pond positioned to the north. A large water reservoir is planned on the eastern side of the plant area. The coal handling area and railway sidings are situated to the west of the main units. The proposed township is located at the southern edge of the project site. The layout plan identifies ten specific boundary coordinates for the project area.

Land and surroundings

The project requires 331.49 hectares of land, of which 15.984 hectares is classified as forest land. The forest area consists of Eco-Class-I Open Forest. The applicant has identified land for compensatory afforestation in Adhuan village, Basudevpur Tehsil, Bhadrak district. Several private entities, including Durjaneeya Land Infracon Pvt Ltd, Dhyutidhara Infracon Private Limited, and Dayalu Developers Private Limited, have provided consent for the transfer of approximately 32.05 acres (12.97 hectares) of land for this purpose.

Water, power and access

Water for the plant will be managed through a comprehensive water balance system. The design includes a raw water reservoir with seven days of storage capacity. The system incorporates a central monitoring basin, a clarified water storage tank, and various treatment plants including a filtration plant, ultra-filtration, and reverse osmosis units. The plant is designed to operate with a closed-cycle cooling system using cooling towers. A coal handling system with a dedicated rail yard will provide the primary fuel access.

Environmental safeguards

The applicant has conducted baseline monitoring for air, water, soil, and noise levels. Air quality monitoring was conducted at 11 locations, focusing on PM10, PM2.5, SO2, NO2, and CO. Noise levels were measured at 11 locations for 24-hour periods. Water sampling was conducted at six surface water and six ground water locations.

To mitigate environmental impact, the project will use ultra-supercritical technology, which is intended to be more efficient than conventional sub-critical plants. The applicant has budgeted ₹178.52 lakh for compensatory afforestation and soil and moisture conservation. A greenbelt will be developed as part of the site plan.

Timeline and economics

The construction phase is estimated to last 60 months (5 years). During this period, the project is expected to employ 275 permanent and 175 temporary workers. Once operational, the plant is projected to provide direct employment to 400 people and indirect employment to 7,800 people over a 35-year operational life.

ItemDetail
Total Capacity2,400 MW (3x800 MW)
TechnologyUltra Super Critical
Construction Period60 months
Permanent Jobs (Construction)275
Direct Jobs (Operation)400
Indirect Jobs (Operation)7,800
Forest Land Diversion15.984 hectares

Orissa Thermal Energy 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power Plant site plan and layout

4 drawings from the project's filings. Sign in free to see them.

Orissa Thermal Energy 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power Plant: Plot plan: units, ash pond, water reservoir, and township layout (preview)🔒 Sign in free to see it
Plot plan: units, ash pond, water reservoir, and township layout
Orissa Thermal Energy 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power Plant: Water balance diagram: treatment systems and circulation flow (preview)🔒 Sign in free to see it
Water balance diagram: treatment systems and circulation flow
Orissa Thermal Energy 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power Plant: Map of ambient air quality sampling locations (preview)🔒 Sign in free to see it
Map of ambient air quality sampling locations
Orissa Thermal Energy 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power Plant: Traffic density map for the study area (preview)🔒 Sign in free to see it
Traffic density map for the study area

In context

43 applications in Cuttack since January 2022 are in the same category (Buildings & townships): 25 approved, 5 filed or under review, and 13 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 819.1 acres, this one is larger than 93% of them.

6 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Rahangol, Khuntuni, Cuttack, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Adani Power Limited in Cuttack

6 Adani Power projects in Cuttack
All 68 Adani Power projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.