Quick answers
What is this project?
Expansion of Aluminium Smelter Production Capacity from 16 LTPA to 18 LTPA, CPP 1215 MW is a lapsed industrial project in Shreepura, Badmal, Jharsuguda, Odisha. The site covers 312.2 acres.
Who is building it?
The applicant is Vedanta Limited.
Has it been approved?
No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.
Where is it?
In Shreepura, Badmal, Jharsuguda, Odisha.
How big is it?
It has a stated cost of ₹1,240 crore and a site of 312.2 acres.
When was it filed?
The application was filed on 24 May 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 29 Oct 2024 |
| Application filed | 24 May 2024 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Industry |
| Applicant | Vedanta Limited |
| Land area | 312.2 acres (126.3 ha) |
| Project cost | ₹1,240 crore |
| Village / locality | Shreepura |
| Taluk / tehsil | Badmal |
| District | Jharsuguda |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-00620 |
In context
38 applications in Jharsuguda since January 2022 are in the same category (Industry): 23 approved, 6 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 312.2 acres, this one is larger than 73% of them.
19 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Shreepura, Badmal, Jharsuguda, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to Talabira II & III: A 23-Million-Tonne-a-Year Coal Mine for Jharsuguda and Sambalpur, Odisha (11.4 km away).
Other projects nearby
- Transfer of the Environmental Clearance and its subsequent amendments/transfer… — environmental approval granted, 0 m away
- Transfer of Environmental Clearance granted for Aluminium Smelter of capacity… — under environmental review, 0 m away
- Proposed Capacity Enhancement of Aluminium Smelter From 18.0 Ltpa to 18.5 Ltpa… — initial checks, 0 m away
- Proposed Capacity Enhancement of Aluminium Smelter From 18.5 Ltpa to 20.0 Ltpa… — initial checks, 0 m away
- Application of ToR for Excavation of Sand from Katikela Sand Bed- A & B (Under… — lapsed, 900 m away
- Katikela Sand Bed-D over an area of 6.07 Ha. at Khata No.- 224. Plot No.-… — under environmental review, 1 km away
- Katikela-A Sand Bed over an area of 10.98 Acres or 4.443 Ha having Khata No.244 — not approved, 1.3 km away
- Katikela-A Sand Quarry — more information requested, 1.3 km away
More from Vedanta Limited in Jharsuguda
- Proposed Capacity Enhancement of Aluminium Smelter From 18.5 Ltpa to 20.0 Ltpa… — initial checks
- Extension of Existing Township (Built-up Area from 3,16,464.3 sqm to… — not approved
- Proposed Capacity Enhancement of Aluminium Smelter From 18.0 Ltpa to 18.5 Ltpa… — initial checks
- For Electrical Installation & Switch Yard for 2400 MW of Thermal Power Plant… — lapsed
- Expansion of Aluminium Smelter Production Capacity from 16 LTPA to 18 LTPA,… — lapsed
- Proposed "WORLD CLASS ALUMINIUM PARK OF VEDANTA" (Special Purpose Vehicle of… — environmental approval granted
7 Vedanta Limited(Division Cairn projects in Jharsuguda
All 76 Vedanta Limited(Division Cairn projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.