What is Developing? Open the mapMap

Initial checksBuildings & townships · Jharsuguda, Odisha

Proposed Capacity Enhancement of Aluminium Smelter From 18.0 Ltpa to 18.5 Ltpa by Optimizing the Production Capacity and Increasing the System Efficiency by Implementing Modern/ Advanced Technology Within the Existing Plant Premises

Proposed Capacity Enhancement of Aluminium Smelter From 18.0 Ltpa to 18.5 Ltpa by Optimizing the Production Capacity and Increasing the System Efficiency by Implementing Modern/ Advanced Technology Within the Existing Plant Premises is a proposed industrial building project in Siri>P>Li, Kolabira, Jharsuguda, Odisha. The site covers 312.2 acres. Its stated project cost is ₹1,240 crore. As of 27 Nov 2026, its status is “Initial checks” (since 23 Nov 2024).

See it on the live map All projects in Jharsuguda

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Proposed Capacity Enhancement of Aluminium Smelter From 18.0 Ltpa to 18.5 Ltpa by Optimizing the Production Capacity and Increasing the System Efficiency by Implementing Modern/ Advanced Technology Within the Existing Plant Premises is a proposed industrial building project in Siri>P>Li, Kolabira, Jharsuguda, Odisha. The site covers 312.2 acres.

Who is building it?

The applicant is Vedanta Limited.

Has it been approved?

Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.

Where is it?

In Siri>P>Li, Kolabira, Jharsuguda, Odisha.

How big is it?

It has a stated cost of ₹1,240 crore and a site of 312.2 acres.

When was it filed?

The application was filed on 23 Nov 2024.

Project details

Official titleProposed Capacity Enhancement of Aluminium Smelter From 18.0 Ltpa to 18.5 Ltpa by Optimizing the Production Capacity and Increasing the System Efficiency by Implementing Modern/ Advanced Technology Within the Existing Plant Premises, at Village- Bhurkamunda, Dist.-Jharsuguda, Odisha by M/S Vedanta Limited.
StatusInitial checks
Status since23 Nov 2024
Application filed23 Nov 2024
Approval soughtEnvironmental approval
Application typeNew project
SectorBuildings & townships
ApplicantVedanta Limited
UseIndustrial
Land area312.2 acres (126.3 ha)
Plot area83,42,360 m² (8,97,96,329 sq ft)
Project cost₹1,240 crore
Village / localitySiri>P>Li
Taluk / tehsilKolabira
DistrictJharsuguda
StateOdisha
Location fromSite boundary on record
Our referenceWID-OR-01199

In context

11 applications in Jharsuguda since January 2022 are in the same category (Buildings & townships): 1 approved, 9 filed or under review, and 1 withdrawn, lapsed or rejected. At 312.2 acres, this one is larger than 82% of them.

20 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Siri>P>Li, Kolabira, Jharsuguda, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Close to Talabira II & III: A 23-Million-Tonne-a-Year Coal Mine for Jharsuguda and Sambalpur, Odisha (11.4 km away).

Other projects nearby

More from Vedanta Limited in Jharsuguda

7 Vedanta Limited(Division Cairn projects in Jharsuguda
All 76 Vedanta Limited(Division Cairn projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.