What is Developing? Open the mapMap

LapsedMining · Kendujhar, Odisha

Nuagaon Iron Ore Mine for Production of 20 MTPA(ROM) of Iron ore with Total Excavation 22.013 MTPA (ROM 20 MTPA + OB/SB/IB 2.013 MTPA) with Screening, Crushing, 4500 TPH Central Processing Unit and 30 MTPA Grinding & Desliming/Beneficiation Plant

Nuagaon Iron Ore Mine for Production of 20 MTPA(ROM) of Iron ore with Total Excavation 22.013 MTPA (ROM 20 MTPA + OB/SB/IB 2.013 MTPA) with Screening, Crushing, 4500 TPH Central Processing Unit and 30 MTPA Grinding & Desliming/Beneficiation Plant is a lapsed mining project in Barapada, Rugudi, Kendujhar, Odisha. The site covers 1,919.9 acres. Its stated project cost is ₹2,483 crore. As of 27 Nov 2026, its status is “Lapsed” (since 14 Sept 2026).

See it on the live map All projects in Kendujhar

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Nuagaon Iron Ore Mine for Production of 20 MTPA(ROM) of Iron ore with Total Excavation 22.013 MTPA (ROM 20 MTPA + OB/SB/IB 2.013 MTPA) with Screening, Crushing, 4500 TPH Central Processing Unit and 30 MTPA Grinding & Desliming/Beneficiation Plant is a lapsed mining project in Barapada, Rugudi, Kendujhar, Odisha. The site covers 1,919.9 acres.

Who is building it?

The applicant is Jsw Steel LTD.

Has it been approved?

No. The application was lapsed on 14 Sept 2026, so it is no longer under consideration.

Where is it?

In Barapada, Rugudi, Kendujhar, Odisha.

How big is it?

It has a stated cost of ₹2,483 crore and a site of 1,919.9 acres.

When was it filed?

The application was filed on 10 Jan 2025.

Project details

Official titleNuagaon Iron Ore Mine for Production of 20 MTPA(ROM) of Iron ore with Total Excavation 22.013 MTPA (ROM 20 MTPA + OB/SB/IB 2.013 MTPA) with Screening, Crushing, 4500 TPH Central Processing Unit and 30 MTPA Grinding & Desliming/Beneficiation Plant along with 30 MTPA Slurry Transportation System in ML area 776.969 ha (DGPS)/767.284 ha (ROR) located at Vill:Nuagaon, Barapada, Gandhalpada, Guali, Katesahi, Parediposi, Kohla Rudukela, Panduliposhi, Topadihi, Tehsil:Barbil, Dist:Keonjhar, State:Odisha
StatusLapsed
Status since14 Sept 2026
Application filed10 Jan 2025
Approval soughtEnvironmental approval
Application typeExpansion
SectorMining
ApplicantJsw Steel LTD
Land area1,919.9 acres (777 ha)
Project cost₹2,483 crore
Village / localityBarapada
Taluk / tehsilRugudi
DistrictKendujhar
StateOdisha
Location fromSite boundary on record
Our referenceWID-OR-00903

In context

213 applications in Kendujhar since January 2022 are in the same category (Mining): 110 approved, 46 filed or under review, and 57 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 1,919.9 acres, this one is larger than 89% of them.

No other mining lease on record is within 500 m of this site; 11 have applied within 5 km.

Where it is

Barapada, Rugudi, Kendujhar, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Jsw Steel LTD in Kendujhar

7 Jsw Steel projects in Kendujhar
All 97 Jsw Steel projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.