Manufacturing of Direct Drawn High Carbon Spring Wire 1.40 Mm to 2.20 Mm, Steel Wire Rope 8 Mm to 22 Mm, Fine Wires 0.60 Mm to 1.30 Mm is a proposed industrial project in Badm>L, Badmal, Jharsuguda, Odisha. The site covers 7.7 acres.
Who is building it?
The applicant is Penguin Trading & Agencies LTD.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 30 May 2024), as of 27 Nov 2026.
Where is it?
In Badm>L, Badmal, Jharsuguda, Odisha.
How big is it?
It has a stated cost of ₹60 crore and a site of 7.7 acres.
When was it filed?
The application was filed on 20 Apr 2024.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 30 May 2024 |
| Application filed | 20 Apr 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Penguin Trading & Agencies LTD |
| Land area | 7.7 acres (3.1 ha) |
| Project cost | ₹60 crore |
| Village / locality | Badm>L |
| Taluk / tehsil | Badmal |
| District | Jharsuguda |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-01757 |
In context
38 applications in Jharsuguda since January 2022 are in the same category (Industry): 23 approved, 6 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 7.7 acres, this one is smaller than 68% of them.
12 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Badm>L, Badmal, Jharsuguda, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to Talabira II & III: A 23-Million-Tonne-a-Year Coal Mine for Jharsuguda and Sambalpur, Odisha (6.7 km away).
Other projects nearby
- Forest Diversion Proposal over 20.950Ac./8.478Ha. Forest Land for the… — under forest review, 1.6 km away
- Provision of Fly Over — more information requested, 1.7 km away
- Iron Ore Pellet Plant of production capacity of 2 X 0.6 MTPA by Konark Ispat… — cleared for impact study, 2.1 km away
- Proposed Integrated Steel Plant of 0.528 MTPA Crude Steel in 103.581 Ha — cleared for impact study, 2.3 km away
- Extension of Existing Township (Built-up Area from 3,16,464.3 sqm to… — not approved, 2.8 km away
- Expansion of Integrated Steel Plant (from 0.5 MTPA to 7.65 MTPA Finished… — initial checks, 3.1 km away
- Expansion of Integrated Steel Plant (from 0.5 MTPA to 7.65 MTPA Finished Steel) — initial checks, 3.1 km away
- Expansion of Integrated Steel Plant (from 0.5 MTPA to 7.65 MTPA Finished Steel) — environmental approval granted, 3.1 km away