Quick answers
What is Bhubaneswari Expansion Ocp 50 Mty?
Bhubaneswari Expansion Ocp 50 Mty is a proposed mining project in Anadipur, Talcher Sadar, Anugul, Odisha. The site covers 2,147.5 acres.
Who is building it?
The applicant is Mahanadi Coalfields Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under forest review”, as of 27 Nov 2026.
Where is it?
In Anadipur, Talcher Sadar, Anugul, Odisha.
How big is it?
It has a stated cost of ₹2,176.7 crore; a site of 2,147.5 acres and 277.1 acres (112.1 ha) of forest land.
When was it filed?
The application was filed on 12 Aug 2026.
Project details
| Status | Under forest review |
|---|---|
| Status since | 10 Sept 2026 |
| Application filed | 12 Aug 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Mining |
| Applicant | Mahanadi Coalfields Limited |
| Land area | 2,147.5 acres (869.1 ha) |
| Forest land | 277.1 acres (112.1 ha) |
| Project cost | ₹2,176.7 crore |
| Village / locality | Anadipur |
| Taluk / tehsil | Talcher Sadar |
| District | Anugul |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-04054 |
In context
108 applications in Anugul since January 2022 are in the same category (Mining): 50 approved, 25 filed or under review, and 33 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 2,147.5 acres, this one is larger than 78% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 4,094.5 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 4 mining leases have applied within 5 km.
Where it is
Anadipur, Talcher Sadar, Anugul, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Bhubaneswari Opencast Expansion Project — environmental approval granted, 450 m away
- Bhubaneswari Opencast Expansion Project — environmental approval granted, 450 m away
- Bhubaneswari Opencast Expansion Project — cleared for impact study, 450 m away
- Ananta Opencast Project — under environmental review, 2.9 km away
- Ananta Open Cast Project — environmental approval granted, 2.9 km away
- Jagannath OCP Expansion — lapsed, 3.7 km away
- Sunakhani Railway Freight Terminal — lapsed, 5.5 km away
- Expansion of Bharatpur Ocp of Existing Capacity 20 Mtpa With Additional Lease… — lapsed, 5.9 km away
More from Mahanadi Coalfields Limited in Anugul
- Integrated Project for Construction of 33 KV Transmission Line From Nandira… — under forest review
- Integrated Project for Construction of 33 KV Transmission Line From 132 KV… — initial checks
- Integrated Project for Construction of 33 KV Transmission Line From 132 KV… — under forest review
- Integrated Project for Construction of 33 KV Transmission Line From Nandira… — initial checks
- Integrated Project for Construction of 33 KV Transmission Line From Nandira… — not approved
- Balabhadra OCP — environmental approval granted
12 Mahanadi Coalfields projects in Anugul
All 23 Mahanadi Coalfields projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.