One of 2 filings for this project. The project's main page, with every filing and where each stands: Diversion of 0.485 ha forest land for Construction of approach road NH-55 to plastic…
Project details
| Status | Lapsed |
|---|---|
| Status since | 13 Dec 2023 |
| Application filed | 15 Mar 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Idco |
| Land area | 1.2 acres (0.5 ha) |
| Forest land | 1.2 acres (0.5 ha) |
| Project cost | ₹150 crore |
| Village / locality | Bhogara |
| Taluk / tehsil | Khuntuni |
| District | Cuttack |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-04557 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 24 Aug 2023 | Forest land use approved | 1.2 acres | ₹150 crore |
| New project filed 15 Mar 2023 (this page) | Lapsed | 1.2 acres | ₹150 crore |
In context
16 applications in Cuttack since January 2022 are in the same category (Roads & highways): 6 approved, 3 filed or under review, and 5 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 1.2 acres, this one is smaller than 100% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bhogara, Khuntuni, Cuttack, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of 0.485 ha forest land for Construction of approach road NH-55 to… — forest land use approved, 0 m away
- Expansion of Steel Plant – DRI Kilns (Sponge Iron from 1,20,000 TPA to… — cleared for impact study, 4.3 km away
- Expansion of Steel Plant – DRI Kilns (Sponge Iron from 1,20,000 TPA to… — environmental approval granted, 4.4 km away
- 3x800 MW Nilanchal Ultra Super Critical Thermal Power Plant (USCTPP) by Orissa… — not approved, 5 km away
- Proposed 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power… — cleared for impact study, 5.1 km away
- Transfer of Terms of Reference (Change in Name) subsequently to NCLT Order… — cleared for impact study, 5.1 km away
- Proposed 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power… — more information requested, 5.1 km away
- Proposed 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power… — cleared for impact study, 5.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.