Project details
| Official title | Diversion of 2.5149 ha of forest land for construction of HEP (2x3=6 MW) on Meyong Chu Stream at Lower Meyong Chu River at Mangan District by Power Deptt. Govt. of Sikkim. |
|---|---|
| Status | Forest land use approved |
| Status since | 20 Apr 2026 |
| Application filed | 30 Jan 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Water & irrigation |
| Applicant | Power Department |
| Land area | 6.2 acres (2.5 ha) |
| Forest land | 6.2 acres (2.5 ha) |
| Project cost | ₹64 crore |
| Village / locality | Naga Forest Block |
| Taluk / tehsil | Mangan |
| District | North District |
| State | Sikkim |
| Location from | Site boundary on record |
| Our reference | WID-SK-00183 |
In context
12 applications in North District since January 2022 are in the same category (Water & irrigation): 9 approved, 0 filed or under review, and 3 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 6.2 acres, this one is smaller than 92% of them.
9 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Naga Forest Block, Mangan, North District, Sikkim. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of 2.5149 ha of forest land for construction of HEP (2x3=6 MW) on… — lapsed, 0 m away
- Teesta Hydroelectric Project Stage-III (1200 MW) — environmental approval granted, 2.3 km away
- Diversion of 3.102 Ha of Forest Land for Rehabilitation Site for Flashflood Or… — not approved, 2.8 km away
- Diversion of 3.058 Ha of forest land for rehabilitation site for flashflood or… — not approved, 2.8 km away
- Diversion of Forest Land Required for Realignment Between Km 80.800 to Km… — lapsed, 2.8 km away
- Diversion of 2.895 ha of forest land for const of 10 MW New Meyong Chu HEP at… — forest land use approved, 3.1 km away
- Re-alignment of 2.79 ha of forest land for const of 10 MW New Meyong Chu HEP… — forest land use approved, 3.4 km away
- Teesta Hydroelectric Project Stage-III (1200 MW) — environmental approval granted, 3.9 km away
More from Power Department in North District
- Divrsion of Forest Land for Extension of Power Supply to Broder Defence Area… — under forest review
- Re-alignment of 2.79 ha of forest land for const of 10 MW New Meyong Chu HEP… — forest land use approved
- Diversion of 0.5252 ha of forest land for part construction of Rabom Chu HEP… — forest land use approved
- Diversion of 2.5149 ha of forest land for construction of HEP (2x3=6 MW) on… — lapsed
- Diversion of 2.895 ha of forest land for const of 10 MW New Meyong Chu HEP at… — forest land use approved
6 Power Department projects in North District
All 16 Power Department projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.