What is Construction of Cavern by 3/11 Gr at General Area of Rajgarh?
Construction of Cavern by 3/11 Gr at General Area of Rajgarh is a proposed project in Kyongnosla Forest Block, Gangtok, East District, Sikkim. The site covers 0.9 acres.
Who is building it?
The applicant is Ministry of Defence.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Kyongnosla Forest Block, Gangtok, East District, Sikkim.
How big is it?
It has a stated cost of ₹7 crore; a site of 0.9 acres and 3,840 m² of forest land.
When was it filed?
The application was filed on 6 Oct 2026.
Project details
| Status | Initial checks |
|---|---|
| Status since | 7 Oct 2026 |
| Application filed | 6 Oct 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Other |
| Applicant | Ministry of Defence |
| Land area | 3,800 m² |
| Forest land | 3,840 m² |
| Project cost | ₹7 crore |
| Village / locality | Kyongnosla Forest Block |
| Taluk / tehsil | Gangtok |
| District | East District |
| State | Sikkim |
| Location from | Site boundary on record |
| Our reference | WID-SK-00228 |
In context
34 applications in East District since January 2022 are in the same category (Other): 1 approved, 13 filed or under review, and 5 withdrawn, lapsed or rejected. At 0.9 acres, this one is smaller than 71% of them.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kyongnosla Forest Block, Gangtok, East District, Sikkim. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of Forest Land of 1.6 Ha from Chola to Yak La Pass for operational… — lapsed, 2.2 km away
- Nature Interpretation Centre at Nathula by Tourism & Civil Aviation… — more information requested, 2.5 km away
- Tourist Infrastructure at Latui RF, Nathula, Kyongnosla T Range under Gangtok… — not approved, 2.5 km away
- Diversion of 10.1 Ha of forest land for Setting up of 5 MW grid connected… — under forest review, 3.5 km away
- Diversion of 10.1 Ha of forest land for Setting up of 5 MW grid connected… — lapsed, 3.5 km away
- Diversion of 10.1 Ha of forest land for Setting up of 5 MW grid connected… — forest land use approved, 3.5 km away
- 5 MW grid connected Solar Photovoltaic Power Plant near Hangu Lake (Phadamchen… — lapsed, 3.5 km away
- Diversion of forest land of 2.38 ha for construction of Rainbow Trout Brood… — more information requested, 4.6 km away
More from Ministry of Defence in East District
- Under Ground Signal Centre at Kupup — decision issued
- Ascon Ph IV MW Site Pt 3777 — decision issued
- Ascon Ph IV MW Site Pt 3777 — more information requested
- Diversion of 191.621 Acres Forest Land Between Milestone-4 to Milestone-13 — lapsed
- Diversion of 1.6 Ha Forest Land at Arjun Fwd -Jelep Cho to Sangae Pp (Sangae… — decision issued
- Diversion of 0.9 Ha Forest Land at Pangolakha Life Life Sanctuary for… — decision issued
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.