Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 8 Mar 2025 |
| Application filed | 14 Jun 2024 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Power |
| Applicant | Tamil Nadu Power Generation Corporation Limited |
| Land area | 190 acres (76.9 ha) |
| Project cost | ₹7,803.4 crore |
| Village / locality | Ennur |
| Taluk / tehsil | Ponneri |
| District | Thiruvallur |
| State | Tamil Nadu |
| Location from | Site boundary on record |
| Our reference | WID-TN-02577 |
In context
14 applications in Thiruvallur since January 2022 are in the same category (Power): 3 approved, 6 filed or under review, and 5 withdrawn, lapsed or rejected. At 190 acres, this one is smaller than 58% of them.
24 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Ennur, Ponneri, Thiruvallur, Tamil Nadu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to Kattupalli Port Expansion: A ₹2,566-Crore Upgrade for Thiruvallur, Tamil Nadu (8.4 km away).
Other projects nearby
- 1x 800 MW NCTPP Stage III by M/s. TNPGCL (Erstwhile TANGEDCO) — lapsed, 0 m away
- EC & CRZ amendment for laying of ash slurry and recovery water pipelines from… — returned to applicant, 2.3 km away
- Laying of Product Operating Line (POL) Pipeline from Kamarajar Port at Ennore… — coastal clearance granted, 2.4 km away
- 2X660 MW Ennore SEZ Thermal Power Plant by M/s. TNPGCL (Erstwhile TANGEDCO) — lapsed, 2.7 km away
- Standalone Cement Grinding Unit with Cement (OPC & PPC) Production Capacity of… — cleared for impact study, 2.8 km away
- Standalone Cement Grinding Unit with Cement (OPC & PPC) Production Capacity of… — cleared for impact study, 2.8 km away
- Validity extension of the Environmental & CRZ Clearance - "Development of… — returned to applicant, 2.9 km away
- 'NIPL' Certification for Proposed Modification & Process Optimisation for… — initial checks, 3 km away
More from Tamil Nadu Power Generation Corporation Limited in Thiruvallur
- 2X660 MW Ennore SEZ Thermal Power Plant by M/s. TNPGCL (Erstwhile TANGEDCO) — lapsed
- 2X660 MW Ennore SEZ Thermal Power Plant by M/s. TNPGCL ( Erstwhile TANGEDCO) — more information requested
- 1x 800 MW NCTPP Stage III by M/s. TNPGCL (Erstwhile TANGEDCO) — lapsed
- 2X660 MW Ennore SEZ Thermal Power Project by M/S. Tamil Nadu Power Generation… — lapsed
- Name Transfer Application Form — lapsed
- 2X660 MW Ennore SEZ Thermal Power Plant by M/s. TNPGCL ( Erstwhile TANGEDCO) — environmental approval granted
11 Tamil Nadu Power Generation Corporation projects in Chennai
All 17 Tamil Nadu Power Generation Corporation projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.