Quick answers
What is this project?
Production Capacity Enhancement of Existing Paper Machine [pm3] (Manufacturing Coated Paper) From 400 Tpd to 490 Tpd and Wood Fiber Line From 300 to 400 Tpd and Replacement of Old Boilers With a New Boiler of 90 Tph Capacity and Co-Generation Power Plant 18.0 MW and Modernization/ Technology Upgradation by Replacement of Old Chemical Recovery Plant With New Chemical Recovery Plant of Capacity 550 Tpd Expandable to 750 Tpd is a proposed power project in Babarkhera, Jaspur, Udham Singh Nagar, Uttarakhand. The site covers 105.9 acres.
Who is building it?
The applicant is Naini Papers Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Babarkhera, Jaspur, Udham Singh Nagar, Uttarakhand.
How big is it?
It has a stated cost of ₹1,445 crore and a site of 105.9 acres.
When was it filed?
The application was filed on 21 Feb 2026.
Project details
| Official title | Production Capacity Enhancement of Existing Paper Machine [pm3] (Manufacturing Coated Paper) From 400 Tpd to 490 Tpd and Wood Fiber Line From 300 to 400 Tpd and Replacement of Old Boilers With a New Boiler of 90 Tph Capacity and Co-Generation Power Plant 18.0 MW and Modernization/ Technology Upgradation by Replacement of Old Chemical Recovery Plant With New Chemical Recovery Plant of Capacity 550 Tpd Expandable to 750 Tpd Along With Lime Kiln of 200 Tpd and 12 MW Co-Generation Power Plant |
|---|---|
| Status | Initial checks |
| Status since | 21 Feb 2026 |
| Application filed | 21 Feb 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Power |
| Applicant | Naini Papers Limited |
| Land area | 105.9 acres (42.9 ha) |
| Project cost | ₹1,445 crore |
| Village / locality | Babarkhera |
| Taluk / tehsil | Jaspur |
| District | Udham Singh Nagar |
| State | Uttarakhand |
| Location from | Site boundary on record |
| Our reference | WID-UK-00893 |
In context
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Babarkhera, Jaspur, Udham Singh Nagar, Uttarakhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Amalgamation & Expansion of Multiply Board/Coated Paper Machine (Pm3) From 400… — lapsed, 0 m away
- Proposed Expansion of Existing Paper Mill (paper manufacturing from waste… — cleared for impact study, 3.4 km away
- Silt/Sand, Bajri & Boulder (RBM) Mining in Dhela River at Khasra No. 1347/5,… — environmental approval granted, 4.6 km away
- Silt/Sand, Bajri & Boulder (RBM) Mining in Dhela River Khasra No. 52/5, 154/2,… — environmental approval granted, 5.1 km away
- Improvement / Upgradation to 4/6 lane Moradabad-Kashipur section of NH 734… — forest land use approved, 6.2 km away
- Kachnalgaji Sand/Silt, Bajri & Boulder (River Bed Material) Deposit at Dhela… — environmental approval granted, 7.1 km away
- Common Solid Waste Management Facility [Sanitary Landfill] at Plot No. 397,… — lapsed, 7.9 km away
- Common Solid Waste Management Facility [Sanitary Landfill] at Plot No. 397,… — cleared for impact study, 7.9 km away
More from Naini Papers Limited in Udham Singh Nagar
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.