Quick answers
What is Sand/Morrum Mine?
Sand/Morrum Mine is a proposed mining project in Pathri, Banda, Uttar Pradesh. The site covers 46.9 acres.
Who is building it?
The applicant is Ravish Gumber.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 19 May 2023), as of 27 Nov 2026.
Where is it?
In Pathri, Banda, Uttar Pradesh.
How big is it?
It has a stated cost of ₹70 lakh and a site of 46.9 acres.
When was it filed?
The application was filed on 19 May 2023.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Sand/Morrum Mine
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 19 May 2023 |
| Application filed | 19 May 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Ravish Gumber |
| Land area | 46.9 acres (19 ha) |
| Project cost | ₹70 lakh |
| Village / locality | Pathri |
| Taluk / tehsil | Banda |
| District | Banda |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-00849 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 30 Oct 2023 | Environmental approval granted | 46.9 acres | ₹70 lakh |
| Early planning filed 19 May 2023 (this page) | Cleared for impact study | 46.9 acres | ₹70 lakh |
In context
231 applications in Banda since January 2022 are in the same category (Mining): 146 approved, 70 filed or under review, and 15 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 46.9 acres, this one is larger than 67% of them.
No other mining lease on record has applied within 5 km of this site.
Where it is
Pathri, Banda, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Sand/Morrum Mine — environmental approval granted, 0 m away
- Project for Construction of Pailani Barrage on Ken River under Ken Betwa Link… — more information requested, 4.5 km away
- Project for Construction of Pailani Barrage on Ken River under Ken Betwa Link… — returned to applicant, 4.5 km away
- Sand/Morrum Mine from Riverbed of Ken River, Village- Marauli Khadar, Gata… — environmental approval granted, 6.3 km away
- Sand/Morrum Mine from Riverbed of Ken River, Village- Marauli Khadar, Gata… — cleared for impact study, 6.3 km away
- Mining project by M/s Descon Buildtech Pvt Ltd — environmental approval granted, 6.9 km away
- Sand/Morrum Mine in Village – Maraulikhader , Tehsil- Banda, District- Banda… — environmental approval granted, 7.3 km away
- Sand/Morrum Mine in Village – Maraulikhader , Tehsil- Banda, District- Banda… — cleared for impact study, 7.3 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.