Quick answers
What is this project?
"Riverbed Sand/Morrum Mining" along riverbed of Yamuna River at Gata No.138, Area-24.24 ha is a proposed mining project in Bichhawali Kachhar, Sikandra, Kanpur Dehat, Uttar Pradesh. The site covers 59.9 acres.
Who is building it?
The applicant is Ajay Chandak.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 10 Jun 2025), as of 27 Nov 2026.
Where is it?
In Bichhawali Kachhar, Sikandra, Kanpur Dehat, Uttar Pradesh.
How big is it?
It has a stated cost of ₹97 lakh and a site of 59.9 acres.
When was it filed?
The application was filed on 6 May 2025.
One of 2 filings for this project. The project's main page, with every filing and where each stands: "Riverbed Sand/Morrum Mining" along riverbed of Yamuna River at Gata No.138, Area-24.24 ha
Project details
| Official title | "Riverbed Sand/Morrum Mining" along riverbed of Yamuna River at Gata No.138, Area-24.24 ha at Village-Bichhawali Kachhar, Tehsil -Sikandara, District- Kanpur Dehat, Uttar Pradesh of Shri Ajay Chandak. |
|---|---|
| Status | Cleared for impact study |
| Status since | 10 Jun 2025 |
| Application filed | 6 May 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Ajay Chandak |
| Land area | 59.9 acres (24.2 ha) |
| Project cost | ₹97 lakh |
| Village / locality | Bichhawali Kachhar |
| Taluk / tehsil | Sikandra |
| District | Kanpur Dehat |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-02889 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 19 Nov 2025 | Environmental approval granted | 59.9 acres | ₹97 lakh |
| Early planning filed 6 May 2025 (this page) | Cleared for impact study | 59.9 acres | ₹97 lakh |
In context
32 applications in Kanpur Dehat since January 2022 are in the same category (Mining): 21 approved, 10 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 7 months from filing to approval. At 59.9 acres, this one is larger than 88% of them.
No other mining lease on record is within 500 m of this site; 3 have applied within 5 km.
Where it is
Bichhawali Kachhar, Sikandra, Kanpur Dehat, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- "Riverbed Sand/Morrum Mining" along riverbed of Yamuna River at Gata No.138,… — environmental approval granted, 0 m away
- "Ordinary Sand Mining" from Riverbed of Yamuna River — under environmental review, 700 m away
- "Sand/Morrum Mine" from Riverbed of Yamuna River — environmental approval granted, 3.3 km away
- "Sand/Morrum Mine" from Riverbed of Yamuna River — cleared for impact study, 3.3 km away
- Riverbed Sand/Morrum Mining" along riverbed of Yamuna river at Gata No.468,… — lapsed, 3.5 km away
- Riverbed Sand/Morrum Mining" along riverbed of Yamuna river at Gata No.468,… — cleared for impact study, 3.5 km away
- Sand/Morrum Deposit Quarry at Khand No.- 01, Gata No. 2059 & 2060, Village-… — environmental approval granted, 6.8 km away
- Sand/Morrum Deposit Quarry at Khand No.- 01, Gata No. 2059 & 2060, Village-… — cleared for impact study, 6.8 km away
More from Ajay Chandak in Kanpur Dehat
- Nibarri Kachhar Sand Mining Project (Area 16.58 Ha) — under environmental review
- Nibarri Kachhar Sand Mining Project (Area 16.58 Ha) — cleared for impact study
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.