Quick answers
What is this project?
"Sand/Morrum Mining" along Betwa Riverbed in Khand No – 22/15, Gata no 35/1, 27/1, 439/3, 445/34, Total Area 24.291ha, Village – Chandaut Dariya, Chandaut Danda, Tehsil- Sarila, District- Hamirpur, U.P of M/s Anandeshwar Tradelinks is a withdrawn mining project in Chandaut Daria, Sarila, Hamirpur, Uttar Pradesh. The site covers 60 acres.
Who is building it?
The applicant is Satya Prakash Gupta.
Has it been approved?
No. The application was withdrawn on 5 Sept 2025, so it is no longer under consideration.
Where is it?
In Chandaut Daria, Sarila, Hamirpur, Uttar Pradesh.
How big is it?
It has a stated cost of ₹56 lakh and a site of 60 acres.
When was it filed?
The application was filed on 5 Sept 2025.
Project details
| Status | Withdrawn |
|---|---|
| Status since | 5 Sept 2025 |
| Application filed | 5 Sept 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Satya Prakash Gupta |
| Land area | 60 acres (24.3 ha) |
| Project cost | ₹56 lakh |
| Village / locality | Chandaut Daria |
| Taluk / tehsil | Sarila |
| District | Hamirpur |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-03021 |
In context
171 applications in Hamirpur since January 2022 are in the same category (Mining): 95 approved, 57 filed or under review, and 19 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 60 acres, this one is larger than 59% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 120 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 6 mining leases have applied within 5 km.
Where it is
Chandaut Daria, Sarila, Hamirpur, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Sand/Morrum Mining along Betwa Riverbed in Khand No. 22/15, Gata no 35/1,… — lapsed, 0 m away
- Sand/Morrum Mining at Betwa River Bed, Gata No.- 35/1, Khand No.-22/14, Area –… — environmental approval granted, 400 m away
- Sand/Morrum Mining at Betwa River Bed, Gata No.- 35/1, Khand No.-22/14, Area –… — cleared for impact study, 400 m away
- Proposed Project of Sand/Morrum Mining from Riverbed of Betwa River at Gata… — under environmental review, 850 m away
- Chandaut Dariya, Chandaut Danda Sand/Morrum Mining Project (12.145Ha) — initial checks, 1.2 km away
- Chandaut Dariya, Chandaut Danda Sand/Morrum Mining Project (12.145Ha) — under environmental review, 1.2 km away
- "Sand/Morrum Mine" from Riverbed of Betwa River, Village- Rirua Basriya,… — environmental approval granted, 1.2 km away
- "Sand/Morrum Mine" from Riverbed of Betwa River, Village- Rirua Basriya,… — cleared for impact study, 1.2 km away
More from Satya Prakash Gupta in Hamirpur
- Sand/Morrum Mining at Betwa River Bed, Gata No.- 35/1, Khand No.-22/14, Area –… — environmental approval granted
- "Sand/Morrum Mining" from Riverbed of Betwa River — environmental approval granted
- "Sand/Morrum Mining" from Riverbed of Betwa River — cleared for impact study
- Sand/Morrum Mining at Betwa River Bed, Gata No.- 35/1, Khand No.-22/14, Area –… — cleared for impact study
- "Sand/Morrum Mining" from Riverbed of Betwa River — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.