What is this project?
Proposed forest land to be diverted for Laying of Drinking Water Pipeline under Amlikaur Group of Villages Drinking Water Scheme of Jal Jeevan Mission of Govt. of India is an approved pipeline project in Bhurendi, Banda, Uttar Pradesh. The site covers 2.8 acres.
Who is building it?
The applicant is Project Manager, Temporary Construction Unit, U.P. Jal Nigam (Rural), Chitrakoot (U.P.).
Has it been approved?
Yes. Its status is “Forest land use approved” (since 14 Mar 2024), as of 27 Nov 2026.
Where is it?
In Bhurendi, Banda, Uttar Pradesh.
How big is it?
It has a stated cost of ₹847.6 crore; a site of 2.8 acres and 1.2 acres (0.5 ha) of forest land.
When was it filed?
The application was filed on 18 Oct 2023.
Project details
| Official title | Proposed forest land to be diverted for Laying of Drinking Water Pipeline under Amlikaur Group of Villages Drinking Water Scheme of Jal Jeevan Mission of Govt. of India, in District:- Banda. |
|---|---|
| Status | Forest land use approved |
| Status since | 14 Mar 2024 |
| Application filed | 18 Oct 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Pipelines |
| Applicant | Project Manager, Temporary Construction Unit, U.P. Jal Nigam (Rural), Chitrakoot (U.P.) |
| Land area | 2.8 acres (1.1 ha) |
| Forest land | 1.2 acres (0.5 ha) |
| Project cost | ₹847.6 crore |
| Village / locality | Bhurendi |
| Taluk / tehsil | Banda |
| District | Banda |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-05435 |
In context
5 applications in Banda since January 2022 are in the same category (Pipelines): 3 approved, 0 filed or under review, and 2 withdrawn, lapsed or rejected.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bhurendi, Banda, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Protected Forest Land proposed to be diverted for the Widening of the Existing… — under forest review, 1.1 km away
- Project for Laying of Carbon Steel Gas Pipe Line (300mm) — forest land use approved, 1.9 km away
- Laying of Carbon Steel Gas Pipe Line (300mm) — lapsed, 3.1 km away
- "Gitti / Patthar" Project at Gata No.- New 360 (Old 918), Village- Mataundh,… — environmental approval granted, 6.3 km away
- Proposed River Bed Sand/Morrum Mining having lease area 10.0 ha (24.71 acre)… — environmental approval granted, 8.3 km away
- Proposed River Bed Sand/Morrum Mining having lease area 10.0 ha (24.71 acre)… — cleared for impact study, 8.3 km away
- "Sand/Morrum Mining" from Riverbed of Ken River Village- Ganchha, Gata No.-… — initial checks, 8.3 km away
- "Sand/Morrum Mining" from Riverbed of Ken River Village- Ganchha, Gata No.-… — under environmental review, 8.3 km away
More from Project Manager, Temporary Construction Unit, U.P. Jal Nigam (Rural), Chitrakoot (U.P.) in Banda
- Proposed forest land to be diverted for Construction of Water Storage Overhead… — forest land use approved
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.