Quick answers
What is this project?
Widening & Strengthening to Two Lane with Paved Shoulder/Four Lane with paved shoulder configuration from Km. 61.500 of NH-727B near Nawalpur (Km, 178.500 of Sonauli-Balia Marg, Old SH-01) i.e. end point of Salempur Bypass to Km. 106.495 of NH-727B near Sikandarpur under EPC mode in the State of Uttar Pradesh." is a proposed road project in Itahura Hajjam, Salempur, Deoria, Uttar Pradesh. The site covers 161.7 acres.
Who is building it?
The applicant is Ministry of Road Transport & Highways.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Itahura Hajjam, Salempur, Deoria, Uttar Pradesh.
How big is it?
It has a stated cost of ₹2,061.9 crore; a site of 161.7 acres and 53.7 acres (21.7 ha) of forest land.
When was it filed?
The application was filed on 29 Apr 2024.
Project details
| Status | More information requested |
|---|---|
| Status since | 29 May 2025 |
| Application filed | 29 Apr 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Ministry of Road Transport & Highways |
| Land area | 161.7 acres (65.4 ha) |
| Forest land | 53.7 acres (21.7 ha) |
| Project cost | ₹2,061.9 crore |
| Village / locality | Itahura Hajjam |
| Taluk / tehsil | Salempur |
| District | Deoria |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-06441 |
In context
8 applications in Deoria since January 2022 are in the same category (Roads & highways): 2 approved, 4 filed or under review, and 2 withdrawn, lapsed or rejected.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Itahura Hajjam, Salempur, Deoria, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Improvement & Upgradation of Section of Km 131.500 to Km 176.485 (44.985 Km)… — forest land use approved, 800 m away
- Proposed protected forest land to be diverted for Entry/Exit approach to IOCL… — lapsed, 6.5 km away
- Salempur Bypass to four lane with paved shoulder configuration from Km. 64.000… — more information requested, 10.5 km away
- Salempur Bypass to four lane with paved shoulder configuration from Km. 64.000… — lapsed, 10.5 km away
- Proposed Forest Land to be Diverted for Entry/Exit Approach to IOCL Retail… — forest land use approved, 13.9 km away
- Proposed Forest Land to be Diverted for Entry/Exit Approach to BPCL Retail… — in-principle approval, conditions pending, 14.4 km away
- Improvement & Upgradation of Section of Km 131.500 to Km 176.485 (44.985 Km)… — lapsed, 15.2 km away
- Rehabilitation & up gradation of Tamkhuiraj – Salempur (NH – 727B) in Deoria… — forest land use approved, 16.3 km away
More from Ministry of Road Transport & Highways in Deoria
- Salempur Bypass to four lane with paved shoulder configuration from Km. 64.000… — more information requested
- Salempur Bypass to four lane with paved shoulder configuration from Km. 64.000… — lapsed
- Deoria Bypass From Existing Km. 27.140 to Existing Km. 46.780 (Design Km.… — more information requested
- Improvement & Upgradation of Section of Km 131.500 to Km 176.485 (44.985 Km)… — forest land use approved
- Rehabilitation & up gradation of Tamkhuiraj – Salempur (NH – 727B) in Deoria… — forest land use approved
- Improvement & Upgradation of Section of Km 131.500 to Km 176.485 (44.985 Km)… — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.