Capacity Augmentation and Safety measures for the Ayodhya-Gorakhpur Section from km 142 800 km to 252 860 on NH-27 in the State of Uttar Pradesh on EPC mode.- Diversion of 25.082 Ha. Protected Forest Land (9.670 ha. under Basti Forest Division, 3.764 Ha. under Sant Kabir Nagar Forest Division and 11.648 Ha. under Gorakhpur Forest Division) for construction of Underpass / Flyover for 12 Nos. of separate Blackspot Locations.

Capacity Augmentation and Safety measures for the Ayodhya-Gorakhpur Section from km 142 800 km to 252 860 on NH-27 in the State of Uttar Pradesh on EPC mode.- Diversion of 25.082 Ha. Protected Forest Land (9.670 ha. under Basti Forest Division, 3.764 Ha. under Sant Kabir Nagar Forest Division and 11.648 Ha. under Gorakhpur Forest Division) for construction of Underpass / Flyover for 12 Nos. of separate Blackspot Locations is a proposed road project in Pikaura Sani, Harraiya, Basti, Uttar Pradesh. The site covers 172.7 acres. Its stated project cost is ₹1,166.2 crore. As of 27 Nov 2026, its status is “More information requested” (since 17 Nov 2026).

See it on the live map All projects in Basti

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Capacity Augmentation and Safety measures for the Ayodhya-Gorakhpur Section from km 142 800 km to 252 860 on NH-27 in the State of Uttar Pradesh on EPC mode.- Diversion of 25.082 Ha. Protected Forest Land (9.670 ha. under Basti Forest Division, 3.764 Ha. under Sant Kabir Nagar Forest Division and 11.648 Ha. under Gorakhpur Forest Division) for construction of Underpass / Flyover for 12 Nos. of separate Blackspot Locations is a proposed road project in Pikaura Sani, Harraiya, Basti, Uttar Pradesh. The site covers 172.7 acres.

Who is building it?

The applicant is National Highway Authority of India.

Has it been approved?

Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.

Where is it?

In Pikaura Sani, Harraiya, Basti, Uttar Pradesh.

How big is it?

It has a stated cost of ₹1,166.2 crore; a site of 172.7 acres and 62 acres (25.1 ha) of forest land.

When was it filed?

The application was filed on 27 Nov 2025.

Project details

StatusMore information requested
Status since17 Nov 2026
Application filed27 Nov 2025
Approval soughtForest land use
Application typeNew project
SectorRoads & highways
ApplicantNational Highway Authority of India
Land area172.7 acres (69.9 ha)
Forest land62 acres (25.1 ha)
Project cost₹1,166.2 crore
Village / localityPikaura Sani
Taluk / tehsilHarraiya
DistrictBasti
StateUttar Pradesh
Location fromSite boundary on record
Our referenceWID-UP-06631

In context

7 applications in Basti since January 2022 are in the same category (Roads & highways): 2 approved, 4 filed or under review, and 1 withdrawn, lapsed or rejected.

1 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Pikaura Sani, Harraiya, Basti, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from National Highway Authority of India in Basti

All 548 National Highways Authority of India (NHAI) projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.