What is this project?
Proposed Forest Land to be Diverted for Entry/Exit approach to HPCL Retail Outlet is a lapsed fuel station in Bari Pura, Mahoba, Uttar Pradesh. The site covers 1.1 acres.
Who is building it?
The applicant is Hindustan Petroleum Corporation Limited (HPCL).
Has it been approved?
No. The application was lapsed on 2 Jun 2025, so it is no longer under consideration.
Where is it?
In Bari Pura, Mahoba, Uttar Pradesh.
How big is it?
It has a stated cost of ₹65 lakh; a site of 1.1 acres and 2,850 m² of forest land.
When was it filed?
The application was filed on 15 Apr 2025.
Project details
| Official title | Proposed Forest Land to be Diverted for Entry/Exit approach to HPCL Retail Outlet at Village:-Baripura, Tehsil:-Mahoba, District:-Mahoba. |
|---|---|
| Status | Lapsed |
| Status since | 2 Jun 2025 |
| Application filed | 15 Apr 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Fuel stations |
| Applicant | Hindustan Petroleum Corporation Limited (HPCL) |
| Land area | 1.1 acres (0.5 ha) |
| Forest land | 2,850 m² |
| Project cost | ₹65 lakh |
| Village / locality | Bari Pura |
| Taluk / tehsil | Mahoba |
| District | Mahoba |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-06649 |
In context
6 applications in Mahoba since January 2022 are in the same category (Fuel stations): 5 approved, 0 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 7 months from filing to approval.
53 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bari Pura, Mahoba, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Indraprastha Gas Limited, Project for Laying of Carbon Steel Gas Pipe Line… — forest land use approved, 1.5 km away
- Project for Laying of Carbon Steel Gas Pipe Line (200mm) — lapsed, 2.2 km away
- Rob at Km. 168+231 on NH-76 With Approaches in the State of Uttar Pradesh on… — more information requested, 2.3 km away
- Proposed "Granite & Dolostone Ballast Gitti" Project at Gata No.- 339 (Khand… — cleared for impact study, 3 km away
- Proposed "Granite & Dolostone Ballast Gitti" Project at Gata No.- 339 (Khand… — environmental approval granted, 3 km away
- Building stone (Granite-Khanda-Boulder-Ballast(Gitty))" Mine at Gata/Arazi… — environmental approval granted, 3.1 km away
- Building stone (Granite-Khanda-Boulder-Ballast(Gitty))" Mine at Gata/Arazi… — cleared for impact study, 3.1 km away
- Building Stone (Khanda,Gitti , Boulder) Mine — environmental approval granted, 3.2 km away
More from Hindustan Petroleum Corporation Limited (HPCL) in Mahoba
- Proposed Forest Land to be Diverted for Entry/Exit approach to HPCL Retail… — forest land use approved
- Proposed Protected Forest Land to be diverted for Entry/Exit approach to HPCL… — forest land use approved
3 Hindustan Petroleum Corporation (HPCL) projects in Mahoba
All 508 Hindustan Petroleum Corporation (HPCL) projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.