Laying of proposed 33 kV Transmission Line from 132/33kV Gurudev Nagar SS to Mirzapur TPP is a proposed power project in Parsauna, Marihan, Mirzapur, Uttar Pradesh. The site covers 0.2 acres.
Who is building it?
The applicant is Adani Power Limited.
Has it been approved?
Not yet. The application is still under review: its status is “In-principle approval, conditions pending”, as of 27 Nov 2026.
Where is it?
In Parsauna, Marihan, Mirzapur, Uttar Pradesh.
How big is it?
It has a stated cost of ₹10 crore; a site of 0.2 acres and 950 m² of forest land.
When was it filed?
The application was filed on 8 Feb 2026.
Project details
| Official title | Laying of proposed 33 kV Transmission Line from 132/33kV Gurudev Nagar SS to Mirzapur TPP at village Dadri Khurd, Tehsil Madihan, Mirzapur, UP by Mirzapur Thermal Energy (UP) Pvt. Ltd. |
|---|---|
| Status | In-principle approval, conditions pending |
| Status since | 12 Jul 2026 |
| Application filed | 8 Feb 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Adani Power Limited |
| Land area | 900 m² |
| Forest land | 950 m² |
| Project cost | ₹10 crore |
| Village / locality | Parsauna |
| Taluk / tehsil | Marihan |
| District | Mirzapur |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-07242 |
In context
5 applications in Mirzapur since January 2022 are in the same category (Power): 3 approved, 2 filed or under review, and 0 withdrawn, lapsed or rejected.
20 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Parsauna, Marihan, Mirzapur, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Maa Vindhyavasini State University, Mirzapur, at Devri Kala, Tehsil -… — lapsed, 1.1 km away
- Proposed protected forest land to be diverted for Entry/Exit approach to… — forest land use approved, 1.8 km away
- Building Stone (Sandstone) at Gata No.- 478, Village- Devri Kalan, Tehsil-… — cleared for impact study, 2.7 km away
- "Building Stone (Sand Stone)" Project at Gata No.- 146, Village- Devarikalan,… — environmental approval granted, 2.8 km away
- Request for Name Change of User Agency from Welspun Energy UP Private Limited… — in-principle approval, conditions pending, 2.8 km away
- "Building stone (Sandstone)" Mine at Arazi/Gata No.- 484, Village– Devri… — environmental approval granted, 3.1 km away
- "Building stone (Sandstone)" Mine at Arazi/Gata No.- 484, Village– Devri… — cleared for impact study, 3.1 km away
- "Building stone (Sandstone)" Mine at Arazi/Gata No.- 484, Village– Devri… — environmental approval granted, 3.2 km away
More from Adani Power Limited in Mirzapur
- Expansion of Mirzapur Thermal Power Plant from 1600 (2x800) MW (Phase I) to… — more information requested
- Residential Township of Mirzapur Thermal Power Plant — initial checks
- Transfer of Environmental Clearance (Change in Name) subsequently to NCLT… — environmental approval granted
- Water Intake Facilities including underground Water Pipeline and Associate… — more information requested
- Railway Siding from Lusa Railway Station to Mirzapur TPP Project Site by Adani… — more information requested
- Request for Name Change of User Agency from Welspun Energy UP Private Limited… — in-principle approval, conditions pending
7 Adani Power projects in Mirzapur
All 68 Adani Power projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.