| Official title | Proposed Installation of Blast Furnace at L.R. Plot No. 2427, 2428, 4654, 4665, 4707, 4672, 4706, 4695, 4655, 4702, 4666, 4699, 4700, 4664, 4698, 4701, 4659, 4660, 4661,4658, 4696, 4704, 4669, 4667, 4674. 4694, 4663, 4703, 4668, 4673, 4697, 4662, Mouza–Bamunara & Gopalpur, J.L No. 58 & 65, P.S – Kanska, District-Paschim Bardhaman, State-West Bengal by M/s Kejriwal Castings Limited |
|---|---|
| Status | Withdrawn |
| Status since | 27 Oct 2025 |
| Application filed | 27 Oct 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Kejriwal Castings Limited |
| Land area | 4.7 acres (1.9 ha) |
| Project cost | ₹200 crore |
| Village / locality | Bamunara |
| Taluk / tehsil | Kanksa |
| District | Paschim Bardhaman |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-01522 |
In context
169 applications in Paschim Bardhaman since January 2022 are in the same category (Industry): 81 approved, 49 filed or under review, and 39 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 4.7 acres, this one is smaller than 93% of them.
31 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bamunara, Kanksa, Paschim Bardhaman, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- "No Increase in Pollution Load" Certificate for configuration change in… — initial checks, 250 m away
- 4 x 20 Tonnes Induction furnaces with Ladle Refining Furnace, CCM and… — lapsed, 250 m away
- 4 x 20 Tonnes Induction furnaces with Ladle Refining Furnace, CCM and… — environmental approval granted, 250 m away
- Expansion of existing steel plant 2 x 6 Tonne to 4 x 25 Tonne Induction… — cleared for impact study, 400 m away
- Proposed Expansion of existing DI Pipe Manufacturing Unit by installation of… — lapsed, 450 m away
- Blast Furnace with Pig Casting Machine, Captive Power Plant, Sinter Plant at… — withdrawn, 450 m away
- Change in Configuration/Modification of existing Induction Furnace from 2x15… — initial checks, 750 m away
- Proposed expansion of existing Steel Plant for replacement of existing 2x7 T… — environmental approval granted, 800 m away
More from Kejriwal Castings Limited in Paschim Bardhaman
- Proposed Expansion of existing DI Pipe Manufacturing Unit by installation of… — lapsed
- Blast Furnace with Pig Casting Machine, Captive Power Plant, Sinter Plant at… — withdrawn