Project details
| Official title | Expansion of Coal Based Ultra Super Critical Thermal Power Plant from 1600 MW to 4000 MW by adding 3x800 MW (Under Phase II) at Tehsil Salboni, District Paschim Medinipur, West Bengal. |
|---|---|
| Status | Under environmental review |
| Status since | 6 Nov 2026 |
| Application filed | 13 Aug 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Power |
| Applicant | Jsw Thermal Energy Limited |
| Land area | 2,085.9 acres (844.1 ha) |
| Project cost | ₹46,070 crore |
| Village / locality | Arabari |
| Taluk / tehsil | Salbani |
| District | Medinipur West |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-01639 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Early planning filed 13 Aug 2026 (this page) | Under environmental review | 2,085.9 acres | ₹46,070 crore |
| Early planning filed 7 Aug 2026 | Withdrawn | 2,085.9 acres | ₹46,070 crore |
In context
11 applications in Medinipur West since January 2022 are in the same category (Power): 2 approved, 5 filed or under review, and 4 withdrawn, lapsed or rejected. At 2,085.9 acres, this one is larger than 64% of them.
Where it is
Arabari, Salbani, Medinipur West, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Coal Based Ultra Super Critical Thermal Power Plant from 1600 MW… — withdrawn, 0 m away
- Underground Cable Laying for Transmission of Power Line From Solar Plant to… — lapsed, 6.5 km away
- Underground Cable Laying for Transmission of Power Line From Solar Plant to… — lapsed, 6.5 km away
- Halder Environmental Controlled Farm — under forest review, 6.5 km away
- Integrated Farming — not approved, 12.2 km away
- Greenfield Project for manufacturing of 300000 TPA Cold Rolling / Galvanized… — not approved, 13.9 km away
- Greenfield Project for manufacturing of 300000 TPA Cold Rolling / Galvanized… — cleared for impact study, 13.9 km away
- Greenfield Integrated steel plant(1.0 MTPA – Million Ton /Annum) consists of… — cleared for impact study, 13.9 km away
More from Jsw Thermal Energy Limited in Medinipur West
- Proposed 2x800 MW Coal Based Ultra Super Critical Thermal Power Plant coming… — environmental approval granted
- Proposed 2x800 MW Coal Based Ultra Super Critical Thermal Power Plant coming… — cleared for impact study
All 4 Jsw Thermal Energy projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.