Project details
| Status | Lapsed |
|---|---|
| Status since | 5 Mar 2024 |
| Application filed | 5 Mar 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Industry |
| Applicant | Captain Industries India Private Limited |
| Land area | 97 acres (39.3 ha) |
| Forest land | 95.4 acres (38.6 ha) |
| Project cost | ₹2,500 crore |
| Village / locality | Bhelaitikri |
| Taluk / tehsil | Garbeta - Iii |
| District | Medinipur West |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-02238 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 5 Mar 2024 (this page) | Lapsed | 97 acres | ₹2,500 crore |
| New project filed 4 Mar 2024 | Not approved | 97 acres | ₹2,500 crore |
In context
43 applications in Medinipur West since January 2022 are in the same category (Industry): 27 approved, 10 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 97 acres, this one is smaller than 56% of them.
5 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bhelaitikri, Garbeta - Iii, Medinipur West, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Integrated Steel Plant with captive Power Plant having capacity of 1 MTPA — not approved, 0 m away
- Greenfield Integrated steel plant(1.0 MTPA – Million Ton /Annum) consists of… — cleared for impact study, 1.3 km away
- Greenfield Project for manufacturing of 300000 TPA Cold Rolling / Galvanized… — not approved, 1.3 km away
- Greenfield Project for manufacturing of 300000 TPA Cold Rolling / Galvanized… — cleared for impact study, 1.3 km away
- Drawal of 11 KV Overhead Line Through Small Portion of Forest Area Near… — more information requested, 3.9 km away
- Drawal of 11 KV Overhead Line Through Small Portion of Forest Area Near… — lapsed, 3.9 km away
- Dhengadaha Morrum Mine — environmental approval granted, 11.3 km away
- [SM/06368] 32 PWSS & 59 Stand Alone PWSS system for Drought Like Situation… — lapsed, 11.8 km away