Raigarh Ispat and Power upcoming projects

Raigarh Ispat and Power Private Limited has filed 5 projects for environmental, forest, wildlife or coastal approval since January 2022: 3 approved and 1 awaiting a decision. They are in Raigarh, covering 761.5 acres with a stated cost of ₹2,774.9 crore. The latest was filed on 18 Dec 2024.

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

5projects filed
1awaiting approval
1districts

All 5 projects, newest first

ProjectTypeSizeStatusFiled
Greenfield steel plant comprising of DRI Kilns (6,93,000 TPA), Induction Furnaces with…
Sivpuri, Raigarh, Chhattisgarh
Industry210.1 acresEnvironmental approval granted18 Dec 2024
Amendments in Existing E.C. Issued to M/S. Raigarh Ispat PVT. LTD. Vide…
Sara\Pali, Raigarh, Chhattisgarh
Industry56.1 acresReturned to applicant30 Nov 2024
TOR amendment -Request for TOR amendment to Exempt Violation for our 90,000 TPA Rolling…
Sara\Pali, Raigarh, Chhattisgarh
Industry85.3 acresLapsed24 Aug 2024
Greenfield steel plant comprising of DRI Kilns (6,93,000 TPA), Induction Furnaces with…
Sivpuri, Raigarh, Chhattisgarh
Industry324.8 acresCleared for impact study22 Jul 2023
Expansion of Steel Plant–Sponge Iron from 1,20,000 TPA to 4,17,000 TPA, MS Ingots/Hot…
Sara\Pali, Raigarh, Chhattisgarh
Industry85.3 acresCleared for impact study20 Apr 2023

Where Raigarh Ispat and Power is building

Questions people ask

How many projects has Raigarh Ispat and Power filed?

5 since January 2022, of which 3 are approved and 1 are awaiting a decision.

Where are Raigarh Ispat and Power's projects?

Mostly in Raigarh, Chhattisgarh (5).

What did Raigarh Ispat and Power file most recently?

Greenfield steel plant comprising of DRI Kilns (6,93,000 TPA), Induction Furnaces with matching LRF & CCM (Hot Billets / Billets - 2,97,000 TPA), Rolling Mill (Rolled Products – 3,30,000 TPA), Ferro Alloy Unit 4 x 9 MVA (FeSi – 28,000 TPA/ FeMn – 1,00,800 TPA/ SiMn – 57,600 TPA/FeCr – 60,000 TPA), Briquetting Plant (400 Kg/Hr),WHRB based Power Plant –48 MW, CFBC based Power Plant - 16 MW & Brick Manufacturing unit (76,000 Bricks / Day) in Sivpuri, Raigarh, filed on 18 Dec 2024. Status: Environmental approval granted.

About this information

Compiled from publicly available approval records, grouped by the applicant's registered name. What is Developing? is not affiliated with Raigarh Ispat and Power; the badge is generated from its name. Group companies that file under different names may appear on separate pages. Statuses can change between our updates; check with the authority before making decisions. Spotted a mistake? Tell us.