Quick answers
What is this project?
Expansion of Steel Plant–Sponge Iron from 1,20,000 TPA to 4,17,000 TPA, MS Ingots/Hot Billets from 90,000 TPA to 2,38,500 TPA, TMT bars/Rolled products from 90,000 TPA to 2,55,000 TPA (or) MS Strip Mill of 1,65,000 TPA (oR) MS Pipe Mill of 1,65,000 TPA, WHRB Power from 8.0 MW to 28 MW, FBC Power from 4 MW to 14MW,Ferro Alloys 2 x 9 MVA (FeSi-14,000 TPA/FeMn-50,400 TPA / SiMn–28,800 TPA/Fecr-30,000 TPA/Pig Iron–50,400 TPA), New Briquetting Plant (200 Kg/hr) & Fly Ash Brick Making unit (55,000 B is a proposed industrial project in Sara\Pali, Tamnar, Raigarh, Chhattisgarh. The site covers 85.3 acres.
Who is building it?
The applicant is Raigarh Ispat and Power Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 20 Apr 2023), as of 27 Nov 2026.
Where is it?
In Sara\Pali, Tamnar, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹489 crore and a site of 85.3 acres.
When was it filed?
The application was filed on 20 Apr 2023.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 20 Apr 2023 |
| Application filed | 20 Apr 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Raigarh Ispat and Power Private Limited |
| Land area | 85.3 acres (34.5 ha) |
| Project cost | ₹489 crore |
| Village / locality | Sara\Pali |
| Taluk / tehsil | Tamnar |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-00694 |
In context
113 applications in Raigarh since January 2022 are in the same category (Industry): 64 approved, 28 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 85.3 acres, this one is larger than 51% of them.
55 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Sara\Pali, Tamnar, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Amendments in Existing E.C. Issued to M/S. Raigarh Ispat PVT. LTD. Vide… — returned to applicant, 100 m away
- TOR amendment -Request for TOR amendment to Exempt Violation for our 90,000… — lapsed, 150 m away
- 132KV Transmission Line from CSPTCL 220/132/33 KV Substation Gerwani to M/s… — lapsed, 800 m away
- Expansion of Steel Plant – DRI Kilns (Sponge Iron from 60,000 TPA to 4,06,500… — environmental approval granted, 2.2 km away
- Expansion of Steel Plant – DRI Kilns (Sponge Iron from 60,000 TPA to 4,06,500… — cleared for impact study, 2.2 km away
- Diversion of Forest Land Proposed for Non-Forest Purpose Under Vss (Van… — lapsed, 2.3 km away
- 132KV Transmission Line from CSPTCL 220/132/33KV Substation Gerwani to M/s… — lapsed, 2.4 km away
- 2 X 95 Tpd Dri Kilns to Manufacture 62,700 Tpa of Sponge Iron, 2 X 3.0 MW of… — environmental approval granted, 2.5 km away
More from Raigarh Ispat and Power Private Limited in Raigarh
- Greenfield steel plant comprising of DRI Kilns (6,93,000 TPA), Induction… — environmental approval granted
- Amendments in Existing E.C. Issued to M/S. Raigarh Ispat PVT. LTD. Vide… — returned to applicant
- TOR amendment -Request for TOR amendment to Exempt Violation for our 90,000… — lapsed
- Greenfield steel plant comprising of DRI Kilns (6,93,000 TPA), Induction… — cleared for impact study
All 5 Raigarh Ispat and Power projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.