What is Expansion of Steel Production from 3.60 MTPA to 4.0 MTPA?
Expansion of Steel Production from 3.60 MTPA to 4.0 MTPA is a proposed industrial project in Gorka, Raigarh, Chhattisgarh. The site covers 1,913 acres.
Who is building it?
The applicant is Jindal Steel & Power LTD.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Gorka, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹9,023.6 crore and a site of 1,913 acres.
When was it filed?
The application was filed on 19 Sept 2023.
Project details
| Status | Initial checks |
|---|---|
| Status since | 19 Sept 2023 |
| Application filed | 19 Sept 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Jindal Steel & Power LTD |
| Land area | 1,913 acres (774.2 ha) |
| Project cost | ₹9,023.6 crore |
| Village / locality | Gorka |
| Taluk / tehsil | Raigarh |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-00273 |
In context
113 applications in Raigarh since January 2022 are in the same category (Industry): 64 approved, 28 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 1,913 acres, this one is larger than 96% of them.
15 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Gorka, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Application for "No Increase in Pollution Load" Certificate for Expansion of… — initial checks, 100 m away
- Transfer of Environmental Clearance granted for Integrated Steel plant (3.6… — environmental approval granted, 600 m away
- Expansion of Existing Integrated Steel Plant From 3.6 Mtpa to 12.6 Mtpa Crude… — under environmental review, 600 m away
- Amendment in Ec for Change in the Project Land of Already Existing Integrated… — lapsed, 700 m away
- Total Area of Land Diverted to Jindal Steel and Power Limited for Non-Forestry… — in-principle approval, conditions pending, 1.1 km away
- Establishment of Cement Plant — under forest review, 1.5 km away
- Establishment of Cement Plant — forest land use approved, 1.5 km away
- Expansion from rail forging unit of capacity 15000 TPA to Integrated Steel… — lapsed, 1.8 km away
All 7 Jindal Steel & Power projects across India