Quick answers
What is this project?
Expansion of existing integrated Steel Plant -DRI Kilns(Sponge Iron 0.6 MTPA to 0.8 MTPA)Power Plant (WHRB 48 MW to 129 MW,AFBC/CFBC9 MW to 124 MW)Existing I/O Beneficiation Plant 2.0 MTPA,Pellet plant 1.4 MTPA, new EOF/BOF and IF with matching capacity of LRF & CCM (2.2 MTPA) , New Sinter Plant (1.2 MTPA), New Coke Oven Plant (0.7 MTPA), New Blast furnace (1250 m3 size)-1.5 MTPA, New Slab/Rolling Mill (Long/Flat)(2.0 MTPA) expansion of Ferro Alloy with AOD(45000 to90000TPA)O2 Plant 24 to 674TPD is a proposed industrial project in Kundru, Tilda, Raipur, Chhattisgarh. The site covers 489.1 acres.
Who is building it?
The applicant is Shri Bajrang Power and Ispat Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 20 Oct 2024), as of 27 Nov 2026.
Where is it?
In Kundru, Tilda, Raipur, Chhattisgarh.
How big is it?
It has a stated cost of ₹4,113.4 crore and a site of 489.1 acres.
When was it filed?
The application was filed on 8 Aug 2024.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Expansion of existing integrated Steel Plant -DRI Kilns(Sponge Iron 0.6 MTPA to 0.8…
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 20 Oct 2024 |
| Application filed | 8 Aug 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Shri Bajrang Power and Ispat Limited |
| Land area | 489.1 acres (197.9 ha) |
| Project cost | ₹4,113.4 crore |
| Village / locality | Kundru |
| Taluk / tehsil | Tilda |
| District | Raipur |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-02097 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 21 Jul 2025 | Environmental approval granted | 489.1 acres | ₹4,113.4 crore |
| Early planning filed 8 Aug 2024 (this page) | Cleared for impact study | 489.1 acres | ₹4,113.4 crore |
In context
219 applications in Raipur since January 2022 are in the same category (Industry): 135 approved, 44 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 489.1 acres, this one is larger than 98% of them.
25 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kundru, Tilda, Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of existing integrated Steel Plant -DRI Kilns(Sponge Iron 0.6 MTPA… — environmental approval granted, 0 m away
- Expansion of Integrated Steel plant-Sponge Iron Plant-0.6 MTPA,Power Plant-125… — lapsed, 0 m away
- Transfer of Environment Clearance vide no. IA-J-11011/88/2023-IA-II(IND-I) dt.… — environmental approval granted, 3 km away
- Proposed Change in the DRI plant configuration from 2 x 200 TPD Kilns to 1 x… — initial checks, 3 km away
- Greenfield Steel plant comprising of Establishment of DRI Kilns (Sponge Iron –… — environmental approval granted, 3 km away
- Greenfield Steel plant comprising of Establishment of DRI Kilns (Sponge Iron –… — cleared for impact study, 3 km away
- EC – Corrigendum for correction in lease area in EC Name change letter No.… — environmental approval granted, 3 km away
- Proposed Change in the DRI plant configuration from 3 x 100 TPD Kilns to 1 x… — initial checks, 3.2 km away
More from Shri Bajrang Power and Ispat Limited in Raipur
- Request for Corrigendum in Environmental Clearance Issued by Seiaa,… — under environmental review
- Transfer of Environmental Clearance (EC) issued to Bajrang Metallics & Power… — environmental approval granted
- Product-mix change (Existing MS Round Bars & CTD Bars to MS Round Bars & TMT… — initial checks
- Expansion of Integrated Steel plant-Sponge Iron Plant-0.6 MTPA,Power Plant-125… — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.