Environmental approval grantedIndustry · Raipur, Chhattisgarh

Expansion of existing integrated Steel Plant -DRI Kilns(Sponge Iron 0.6 MTPA to 0.8 MTPA)Power Plant (WHRB 48 MW to 129 MW,AFBC/CFBC9 MW to 124 MW)Existing I/O Beneficiation Plant 2.0 MTPA,Pellet plant 1.4 MTPA, new EOF/BOF and IF with matching capacity of LRF & CCM (2.2 MTPA) , New Sinter Plant (1.2 MTPA), New Coke Oven Plant (0.7 MTPA), New Blast furnace (1250 m3 size)-1.5 MTPA, New Slab/Rolling Mill (Long/Flat)(2.0 MTPA) expansion of Ferro Alloy with AOD(45000 to90000TPA)O2 Plant 24 to 674TPD

Expansion of existing integrated Steel Plant -DRI Kilns(Sponge Iron 0.6 MTPA to 0.8 MTPA)Power Plant (WHRB 48 MW to 129 MW,AFBC/CFBC9 MW to 124 MW)Existing I/O Beneficiation Plant 2.0 MTPA,Pellet plant 1.4 MTPA, new EOF/BOF and IF with matching capacity of LRF & CCM (2.2 MTPA) , New Sinter Plant (1.2 MTPA), New Coke Oven Plant (0.7 MTPA), New Blast furnace (1250 m3 size)-1.5 MTPA, New Slab/Rolling Mill (Long/Flat)(2.0 MTPA) expansion of Ferro Alloy with AOD(45000 to90000TPA)O2 Plant 24 to 674TPD is an approved industrial project in Kundru, Tilda, Raipur, Chhattisgarh. The site covers 489.1 acres. Its stated project cost is ₹4,113.4 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 22 Apr 2026).

See it on the live map All projects in Raipur

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Expansion of existing integrated Steel Plant -DRI Kilns(Sponge Iron 0.6 MTPA to 0.8 MTPA)Power Plant (WHRB 48 MW to 129 MW,AFBC/CFBC9 MW to 124 MW)Existing I/O Beneficiation Plant 2.0 MTPA,Pellet plant 1.4 MTPA, new EOF/BOF and IF with matching capacity of LRF & CCM (2.2 MTPA) , New Sinter Plant (1.2 MTPA), New Coke Oven Plant (0.7 MTPA), New Blast furnace (1250 m3 size)-1.5 MTPA, New Slab/Rolling Mill (Long/Flat)(2.0 MTPA) expansion of Ferro Alloy with AOD(45000 to90000TPA)O2 Plant 24 to 674TPD is an approved industrial project in Kundru, Tilda, Raipur, Chhattisgarh. The site covers 489.1 acres.

Who is building it?

The applicant is Shri Bajrang Power and Ispat Limited.

Has it been approved?

Yes. Its status is “Environmental approval granted” (since 22 Apr 2026), as of 27 Nov 2026.

Where is it?

In Kundru, Tilda, Raipur, Chhattisgarh.

How big is it?

It has a stated cost of ₹4,113.4 crore and a site of 489.1 acres.

When was it filed?

The application was filed on 21 Jul 2025.

Project details

StatusEnvironmental approval granted
Status since22 Apr 2026
Application filed21 Jul 2025
Approval soughtEnvironmental approval
Application typeExpansion
SectorIndustry
ApplicantShri Bajrang Power and Ispat Limited
Land area489.1 acres (197.9 ha)
Project cost₹4,113.4 crore
Village / localityKundru
Taluk / tehsilTilda
DistrictRaipur
StateChhattisgarh
Location fromSite boundary on record
Our referenceWID-CG-02372

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Expansion filed 21 Jul 2025 (this page)Environmental approval granted489.1 acres₹4,113.4 crore
Early planning filed 8 Aug 2024Cleared for impact study489.1 acres₹4,113.4 crore

In context

219 applications in Raipur since January 2022 are in the same category (Industry): 135 approved, 44 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 489.1 acres, this one is larger than 98% of them.

25 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Kundru, Tilda, Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Shri Bajrang Power and Ispat Limited in Raipur

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.