Quick answers
What is this project?
Amendment in Environmental Clearance for Enhancement in Power Generation Capacity of our Siltara Power Plant from Restricted Capacity of 81.5 MW to 98.7 MW is a withdrawn power project in Siltara, Raipur, Chhattisgarh. The site covers 167.9 acres.
Who is building it?
The applicant is Sarda Energy & Minerals Limited.
Has it been approved?
No. The application was withdrawn on 18 Nov 2025, so it is no longer under consideration.
Where is it?
In Siltara, Raipur, Chhattisgarh.
How big is it?
It has a stated cost of ₹42.9 crore and a site of 167.9 acres.
When was it filed?
The application was filed on 18 Nov 2025.
Project details
| Status | Withdrawn |
|---|---|
| Status since | 18 Nov 2025 |
| Application filed | 18 Nov 2025 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Power |
| Applicant | Sarda Energy & Minerals Limited |
| Land area | 167.9 acres (68 ha) |
| Project cost | ₹42.9 crore |
| Village / locality | Siltara |
| Taluk / tehsil | Raipur |
| District | Raipur |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-02778 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Amendment filed 18 Nov 2025 (this page) | Withdrawn | 167.9 acres | ₹42.9 crore |
| Amendment filed 13 Nov 2025 | Lapsed | 151.3 acres | ₹42.9 crore |
In context
13 applications in Raipur since January 2022 are in the same category (Power): 4 approved, 8 filed or under review, and 1 withdrawn, lapsed or rejected. At 167.9 acres, this one is smaller than 69% of them.
48 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Siltara, Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Amendment in Environmental Clearance for Enhancement in Power Generation… — lapsed, 0 m away
- Amendment in Environmental Clearance for Enhancement in Power Generation… — returned to applicant, 0 m away
- Expansion of existing Plant with Augmentation of existing Induction Furnace… — cleared for impact study, 750 m away
- Expansion of existing Plant with Augmentation of existing Induction Furnace… — not approved, 750 m away
- Expansion Proposal of Iron Ore Beneficiation Plant from 3.284 MTPA to 5.657… — environmental approval granted, 1.1 km away
- Expansion Proposal of Iron Ore Beneficiation Plant from 3.284 MTPA to 5.657… — cleared for impact study, 1.1 km away
- Expansion Proposal of Iron Ore Beneficiation Plant from 3.284 MTPA to 5.657… — environmental approval granted, 1.1 km away
- Enhancement in production of Sponge Iron from 650000 TPA to 715000 TPA through… — initial checks, 1.1 km away
3 Sarda Energy & Minerals projects in Raipur
All 20 Sarda Energy & Minerals projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.