Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 12 Nov 2025 |
| Application filed | 3 Oct 2025 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Buildings & townships |
| Applicant | Semifab Private Limited |
| Use | Industrial |
| Land area | 119.7 acres (48.4 ha) |
| Project cost | ₹40,610.4 crore |
| Village / locality | Dholera |
| Taluk / tehsil | Dholera |
| District | Ahmadabad |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-07765 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Ownership transfer filed 3 Oct 2025 (this page) | Environmental approval granted | 119.7 acres | ₹40,610.4 crore |
| New project filed 21 Nov 2024 | Environmental approval granted | 119.7 acres | ₹40,610.4 crore |
In context
1,175 applications in Ahmadabad since January 2022 are in the same category (Buildings & townships): 916 approved, 201 filed or under review, and 58 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 119.7 acres, this one is larger than 96% of them.
10 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Dholera, Ahmadabad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to Blueparrot Data Centre: 813 MW Data Centre Building Project in Dholera, Gujarat (1.7 km away).
Other projects nearby
- Semiconductor Wafer Fabrication — environmental approval granted, 0 m away
- Expansion of Semiconductor Wafer Fabrication Project — under environmental review, 150 m away
- Environment Clearance for proposed Factory Building construction project for… — environmental approval granted, 650 m away
- Environment Clearance for proposed Factory Building construction project for… — initial checks, 650 m away
- Shantiban Skylar — initial checks, 750 m away
- Proposed Residential & Commercial Building Project namely "Akhilam" by Parjiya… — environmental approval granted, 800 m away
- Data Centre Building project by Blueparrot Pedestal Limited — under environmental review, 1.7 km away
- 8" dia. Steel Gas pipeline from End Point of Dhandhuka-Dholera Pipeline Near… — forest land use approved, 2.9 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.