| Official title | Construction of an approach roads for Smart Homes Infrastructure Pvt Limited Dholera, district Ahmedabad |
|---|---|
| Status | Forest land use approved |
| Status since | 6 Apr 2026 |
| Application filed | 7 Apr 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Smarthomes Infrastructreprivate Limited |
| Land area | 500 m² |
| Forest land | 530 m² |
| Project cost | ₹20 crore |
| Village / locality | Kamatalav |
| Taluk / tehsil | Dholera |
| District | Ahmadabad |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-11994 |
In context
20 applications in Ahmadabad since January 2022 are in the same category (Roads & highways): 2 approved, 12 filed or under review, and 6 withdrawn, lapsed or rejected. At 0.1 acres, this one is smaller than 95% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kamatalav, Dholera, Ahmadabad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to Blueparrot Data Centre: 813 MW Data Centre Building Project in Dholera, Gujarat (14 km away).
Other projects nearby
- Link Road from Proposed Ahmedabad -Dholera Expressway to Proposed Dholera… — recommended by coastal authority, 3.6 km away
- Diversion of 20.2286 ha. of RESERVED forest land for work of GETCO 400kV D/C… — more information requested, 6.3 km away
- Construction for Missing link in between Vadgam (Ta. Khambhat, Dist. Anand) to… — recommended by coastal authority, 8.4 km away
- 8" dia. Steel Gas pipeline from End Point of Dhandhuka-Dholera Pipeline Near… — forest land use approved, 10.5 km away
- Shantiban Skylar — initial checks, 12.1 km away
- Environment Clearance for proposed Factory Building construction project for… — environmental approval granted, 12.3 km away
- Expansion of Semiconductor Wafer Fabrication Project — under environmental review, 12.4 km away
- Environment Clearance for proposed Factory Building construction project for… — initial checks, 12.4 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.