Quick answers
What is this project?
Diversion of Forest Land for the Laying of Proposed Underground Water Pipeline and Construction of Sump and Pump House in Favor of Gujarat Water Supply & Sewerage Board, Public Health Sanitary Sub Division Nakhatrana of Kutch District of the State of Gujarat is a lapsed pipeline project in Aral Moti, Nakhatrana, Kachchh, Gujarat. The site covers 2.7 acres.
Who is building it?
The applicant is Gujarat Water Supply & Sewerage Board, P.H..S Sub Dn. No.1 Naliya.
Has it been approved?
No. The application was lapsed on 28 Aug 2024, so it is no longer under consideration.
Where is it?
In Aral Moti, Nakhatrana, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹15 crore; a site of 2.7 acres and 2.7 acres (1.1 ha) of forest land.
When was it filed?
The application was filed on 25 Sept 2023.
Project details
| Status | Lapsed |
|---|---|
| Status since | 28 Aug 2024 |
| Application filed | 25 Sept 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Pipelines |
| Applicant | Gujarat Water Supply & Sewerage Board, P.H..S Sub Dn. No.1 Naliya |
| Land area | 2.7 acres (1.1 ha) |
| Forest land | 2.7 acres (1.1 ha) |
| Project cost | ₹15 crore |
| Village / locality | Aral Moti |
| Taluk / tehsil | Nakhatrana |
| District | Kachchh |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-12354 |
In context
59 applications in Kachchh since January 2022 are in the same category (Pipelines): 21 approved, 25 filed or under review, and 13 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 2.7 acres, this one is larger than 62% of them.
7 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Aral Moti, Nakhatrana, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Jadeja Surtaji Hamirji — environmental approval granted, 1.2 km away
- Diversion of 0.8526 Ha Forest land for the laying of Proposed Underground… — lapsed, 3.8 km away
- Proposed for Laying of Proposed Underground Water Pipeline in Favor of Gwssb… — more information requested, 3.8 km away
- Diversion of Roadside Protected Forest Land for Construction of 33 KV… — forest land use approved, 4.7 km away
- Diversion of 0.03 Ha. Protected forest land of Kutch Social Forestry Division… — forest land use approved, 4.7 km away
- Diversion of 0.026 Ha. Protected forest land of Kutch Social Forestry Division… — forest land use approved, 4.7 km away
- K.P. Energy Limited Want to Construct 33 KV Overhead Transmission Line Which… — forest land use approved, 4.7 km away
- Diversion of 0.075 Ha Reserved Forest Land of Kutch (West) Forest Division of… — lapsed, 5.4 km away
More from Gujarat Water Supply & Sewerage Board, P.H..S Sub Dn. No.1 Naliya in Kachchh
- Diversion of Forest land of Village: Laiyari( Ta: Abdasa) and Village: Maniara… — more information requested
- Diversion of 0.3490 Ha Forest Land of Naliya Narayansarovar Road for Laying of… — more information requested
- Diversion of 0.4627 Ha Forest land of Naliya Narayansarovar Road for laying of… — more information requested
- Diversion of Forest land for the laying of Proposed Underground Water Pipeline… — forest land use approved
- Diversion of Forest Land for Laying of Underground Water Pipeline and… — forest land use approved
- Laying of Underground Water Pipeline to Roadside Forest of Bhuj Khavada Road — more information requested
All 28 Gujarat Water Supply & Sewerage Board, P.H..S Sub Dn. No.1 Naliya projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.