Forest land use approvedPower · Kachchh, Gujarat

Forest Clearance Proposal for laying of 66 KV 1C, 630 sq. mm (3+1) XLPE Underground Power Cable from 66 KV Bhuj-A Substation to 66 KV Bhuj-C Substation under Kishan Suryoday Yojana-2 (KSY-2)

Forest Clearance Proposal for laying of 66 KV 1C, 630 sq. mm (3+1) XLPE Underground Power Cable from 66 KV Bhuj-A Substation to 66 KV Bhuj-C Substation under Kishan Suryoday Yojana-2 (KSY-2) is an approved power project in Mirjapar, Bhuj, Kachchh, Gujarat. The site covers 0.1 acres. Its stated project cost is ₹3.4 crore. As of 27 Nov 2026, its status is “Forest land use approved” (since 6 Apr 2026).

See it on the live map All projects in Kachchh

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Forest Clearance Proposal for laying of 66 KV 1C, 630 sq. mm (3+1) XLPE Underground Power Cable from 66 KV Bhuj-A Substation to 66 KV Bhuj-C Substation under Kishan Suryoday Yojana-2 (KSY-2) is an approved power project in Mirjapar, Bhuj, Kachchh, Gujarat. The site covers 0.1 acres.

Who is building it?

The applicant is Gujarat Energy Transmission Corp LTD.

Has it been approved?

Yes. Its status is “Forest land use approved” (since 6 Apr 2026), as of 27 Nov 2026.

Where is it?

In Mirjapar, Bhuj, Kachchh, Gujarat.

How big is it?

It has a stated cost of ₹3.4 crore; a site of 0.1 acres and 480 m² of forest land.

When was it filed?

The application was filed on 11 Dec 2025.

Project details

StatusForest land use approved
Status since6 Apr 2026
Application filed11 Dec 2025
Approval soughtForest land use
Application typeNew project
SectorPower
ApplicantGujarat Energy Transmission Corp LTD
Land area500 m²
Forest land480 m²
Project cost₹3.4 crore
Village / localityMirjapar
Taluk / tehsilBhuj
DistrictKachchh
StateGujarat
Location fromSite boundary on record
Our referenceWID-GJ-12520

In context

75 applications in Kachchh since January 2022 are in the same category (Power): 30 approved, 30 filed or under review, and 11 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 0.1 acres, this one is smaller than 87% of them.

3 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Mirjapar, Bhuj, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Gujarat Energy Transmission Corp LTD in Kachchh

43 Gujarat Energy Transmission Corp projects in Kachchh
All 231 Gujarat Energy Transmission Corp projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.