What is this project?
Proposal to grant permission for laying Optical Fiber Cable along the road in Protected Forest (7.91 Ha) and Reserve Forest (0.29 Ha) area in the villages of Vyara, Valod, Songadh, Uchchhal, Nizar and Kukarmunda Taluka of Tapi District for Gujarat Fiber Grid Network Ltd. (Total 8.20 Hec) is a proposed telecom project in Khodada, Nizar, Tapi, Gujarat. The site covers 20.3 acres.
Who is building it?
The applicant is Gfgnl.
Has it been approved?
Not yet. The application is still under review: its status is “Under forest review”, as of 27 Nov 2026.
Where is it?
In Khodada, Nizar, Tapi, Gujarat.
How big is it?
It has a stated cost of ₹280 crore; a site of 20.3 acres and 20.3 acres (8.2 ha) of forest land.
When was it filed?
The application was filed on 20 Nov 2026.
Project details
| Status | Under forest review |
|---|---|
| Status since | 21 Nov 2026 |
| Application filed | 20 Nov 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Telecom |
| Applicant | Gfgnl |
| Land area | 20.3 acres (8.2 ha) |
| Forest land | 20.3 acres (8.2 ha) |
| Project cost | ₹280 crore |
| Village / locality | Khodada |
| Taluk / tehsil | Nizar |
| District | Tapi |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-12991 |
In context
24 applications in Tapi since January 2022 are in the same category (Telecom): 9 approved, 4 filed or under review, and 11 withdrawn, lapsed or rejected. The approved ones took a median of 8 months from filing to approval. At 20.3 acres, this one is larger than 95% of them.
Where it is
Khodada, Nizar, Tapi, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Laying of 66kV 630 sq mm (3+1) XLPE Underground cable for 66KV Uchchhal –… — forest land use approved, 9.3 km away
- Proposal of 0.253 Hectare Reserved Forest Land for Required Area Built Up New… — under forest review, 9.7 km away
- Tapi 4G Sat USOF — forest land use approved, 9.9 km away
- Tapi 4G Sat USO — lapsed, 9.9 km away
- Laying OFC for 4G coverage of uncovered villages through USOF, Babarghat T… — lapsed, 11.1 km away
- Diversion of 0.538 Hectors. Reserved Forest Land for the Grant Permission for… — forest land use approved, 11.5 km away
- Widening and Strengthening Of Boarda-Satkashi-Sherulla (Km. 0/000 To 29/500).… — lapsed, 11.9 km away
- Widening and Strengthening Of Boarda-Satkashi-Sherulla (Km. 0/000 To 29/500).… — more information requested, 11.9 km away
More from Gfgnl in Tapi
- Proposal to grant permission for laying Optical Fiber Cable in Uchchhal, Nizar… — lapsed
- Proposal to grant permission for laying Optical Fiber Cable of Vyara, Valod… — lapsed
- Proposal for Grant of Permission for Laying Ofc Along With the Routes… — in-principle approval, conditions pending
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.