Quick answers
What is this project?
Modification-cum-Expansion of Ferro Alloy Plant (under violation) Modification of existing 2x5 MVA SEAF's to 2x6 MVA SEAF, Modification of existing 1x7.5 MVA SEAF to 1x9 MVA SEAF, Existing 1x9.0 MVA SEAF, establishment new 1x9 MVA SEAF & new 12MT per batch CLU Converter for refining liquid HC FeMn to MC/LC FeMn by BIHAR FOUNDRY & CASTINGS LIMITED is a proposed industrial project in Marar, Ramgarh, Jharkhand. The site covers 10.6 acres.
Who is building it?
The applicant is Bihar Foundry and Castings Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Marar, Ramgarh, Jharkhand.
How big is it?
It has a stated cost of ₹124.3 crore and a site of 10.6 acres.
When was it filed?
The application was filed on 8 Feb 2023.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 8 Feb 2023 |
| Application filed | 8 Feb 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Bihar Foundry and Castings Limited |
| Land area | 10.6 acres (4.3 ha) |
| Project cost | ₹124.3 crore |
| Village / locality | Marar |
| Taluk / tehsil | Ramgarh |
| District | Ramgarh |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-00157 |
In context
30 applications in Ramgarh since January 2022 are in the same category (Industry): 12 approved, 10 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 31 days from filing to approval. At 10.6 acres, this one is smaller than 73% of them.
20 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Marar, Ramgarh, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Industrial project by Bihar Foundry and Castings Limited — under environmental review, 0 m away
- Industrial project by Bihar Foundry and Castings Limited — cleared for impact study, 0 m away
- Exapansion of steel plant –Sponge Iron through DRI Klins from 99,000 TPA to… — cleared for impact study, 350 m away
- Exapansion of steel plant –Sponge Iron through DRI Klins from 99,000 TPA to… — environmental approval granted, 350 m away
- Forest Diversion of 3.94 hectare of land for M/s Bihar Foundry & Castings… — under forest review, 800 m away
- Bihar foundry & Castings ltd. Water Pipe line from Damodar river — in-principle approval, conditions pending, 850 m away
- Underground 33 KV transmission line from existing location no. 19 of Giddi… — forest land use approved, 1.2 km away
- BFCL - Water Pipe Line From Damodar River — lapsed, 1.7 km away
More from Bihar Foundry and Castings Limited in Ramgarh
- Forest Diversion of 3.94 hectare of land for M/s Bihar Foundry & Castings… — under forest review
- Bihar foundry & Castings ltd. Water Pipe line from Damodar river — in-principle approval, conditions pending
- Exapansion of steel plant –Sponge Iron through DRI Klins from 99,000 TPA to… — cleared for impact study
- Exapansion of steel plant –Sponge Iron through DRI Klins from 99,000 TPA to… — environmental approval granted
- BFCL - Water Pipe Line From Damodar River — lapsed
- Industrial project by Bihar Foundry and Castings Limited — under environmental review
All 8 Bihar Foundry and Castings projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.