Quick answers
What is this project?
Request for transfer of Environment Clearance/ change of name from M/s. SHRI SAI PRIYA SUGARS LIMITED to M/s. MRN CHAMUNDI CANEPOWER AND BIOREFINERIES PRIVATE LIMITED, UNIT – 2 in the environmental clearance granted to M/s. Shri Sai Priya Sugars Ltd., for expansion of sugarcane crushing capacity from 10000 TCD to 15000 TCD, co-generation power plant of 65 MW vide EC no. J-11011/277/2010-IA II(I) dated 16.06.2023 is an approved industrial project in Alabal, Jamkhandi, Bagalkote, Karnataka. The site covers 148.4 acres.
Who is building it?
The applicant is Shri Sai Priya Sugars Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 3 May 2024), as of 27 Nov 2026.
Where is it?
In Alabal, Jamkhandi, Bagalkote, Karnataka.
How big is it?
It has a stated cost of ₹635.1 crore and a site of 148.4 acres.
When was it filed?
The application was filed on 1 Mar 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 3 May 2024 |
| Application filed | 1 Mar 2024 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Industry |
| Applicant | Shri Sai Priya Sugars Limited |
| Land area | 148.4 acres (60.1 ha) |
| Project cost | ₹635.1 crore |
| Village / locality | Alabal |
| Taluk / tehsil | Jamkhandi |
| District | Bagalkote |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-02107 |
In context
61 applications in Bagalkote since January 2022 are in the same category (Industry): 39 approved, 11 filed or under review, and 11 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 148.4 acres, this one is larger than 77% of them.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Alabal, Jamkhandi, Bagalkote, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environmental Clearance From M/s MRN Chamundi Cane Power and… — environmental approval granted, 100 m away
- Amendment in Environment Clearances Condition Granted to Sugar & Cogen Complex… — environmental approval granted, 100 m away
- Addition of Grain as a Raw Material in 600 KLPD Distillery based on B/C Heavy… — initial checks, 400 m away
- Use of Additional Feedstock – Grain in Addition to the Existing Feedstocks… — lapsed, 400 m away
- Multi Village Water Supply Scheme to All Rural Habitations in Jamakhandi and… — lapsed, 6.9 km away
- Diversion of 0.187 Ha. of Forest Land — initial checks, 9.5 km away
- Diversion of Forest Land — lapsed, 9.6 km away
- Diversion of Forest Land — lapsed, 9.6 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.