Quick answers
What is this project?
Use of Additional Feedstock – Grain in Addition to the Existing Feedstocks Viz. Sugarcane Syrup/B Heavy Molasses/C Heavy Molasses in the Distillery Plant to Produce Ethanol of 500 Klpd Capacity by M/S Trualt Bioenergy Limited Unit-2 is a lapsed industrial project in Alabal, Jamkhandi, Bagalkote, Karnataka. The site covers 26.7 acres.
Who is building it?
The applicant is Trualt Bioenergy Limited.
Has it been approved?
No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.
Where is it?
In Alabal, Jamkhandi, Bagalkote, Karnataka.
How big is it?
It has a stated cost of ₹472.5 crore and a site of 26.7 acres.
When was it filed?
The application was filed on 25 Apr 2024.
Project details
| Official title | Use of Additional Feedstock – Grain in Addition to the Existing Feedstocks Viz. Sugarcane Syrup/B Heavy Molasses/C Heavy Molasses in the Distillery Plant to Produce Ethanol of 500 Klpd Capacity Under Ebp Scheme by M/S Trualt Bioenergy Limited Unit-2 |
|---|---|
| Status | Lapsed |
| Status since | 29 Oct 2024 |
| Application filed | 25 Apr 2024 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Trualt Bioenergy Limited |
| Land area | 26.7 acres (10.8 ha) |
| Project cost | ₹472.5 crore |
| Village / locality | Alabal |
| Taluk / tehsil | Jamkhandi |
| District | Bagalkote |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-01600 |
In context
61 applications in Bagalkote since January 2022 are in the same category (Industry): 39 approved, 11 filed or under review, and 11 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 26.7 acres, this one is smaller than 85% of them.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Alabal, Jamkhandi, Bagalkote, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Addition of Grain as a Raw Material in 600 KLPD Distillery based on B/C Heavy… — initial checks, 0 m away
- Request for transfer of Environment Clearance/ change of name from M/s. SHRI… — environmental approval granted, 400 m away
- Transfer of Environmental Clearance From M/s MRN Chamundi Cane Power and… — environmental approval granted, 450 m away
- Amendment in Environment Clearances Condition Granted to Sugar & Cogen Complex… — environmental approval granted, 450 m away
- Multi Village Water Supply Scheme to All Rural Habitations in Jamakhandi and… — lapsed, 6.8 km away
- Diversion of 0.187 Ha. of Forest Land — initial checks, 9.8 km away
- Diversion of Forest Land — lapsed, 9.9 km away
- Diversion of Forest Land — lapsed, 9.9 km away
More from Trualt Bioenergy Limited in Bagalkote
- Expansion of 200 KLPD ENA/RS/Ethanol with cane syrup/molasses based to 700… — cleared for impact study
- Expansion of Distillery from 120 KLPD to 700 KLPD for manufacturing of RS/… — returned to applicant
- Manufacturing of RS/ ENA/ Industrial Alcohol / Sustainable Aviation Fuel (SAF)… — cleared for impact study
- Proposed 500 KLPD Multi-feed (B-Heavy Molasses/C-Heavy Molasses/Cane… — returned to applicant
- Expansion of Distillery for Ethanol Production Under Ebp Program From 700 Kld… — environmental approval granted
- Proposed 500 KLPD Multi-feed (B-Heavy Molasses/C-Heavy Molasses/Cane… — environmental approval granted
All 10 Trualt Bioenergy projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.