Quick answers
What is this project?
Environmental Clearance for Basalt Stone Quarry having area 2.00 Ha of Shri. Vishwanath Yadu Nalwade Located at gut no. 624 Part, Village- Kokrale, Taluka- Khatav, Distict- Satara is an approved mining project in Kokarale, Khatav, Satara, Maharashtra. The site covers 4.9 acres.
Who is building it?
The applicant is Vishwanath Yadu Nalwade.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 11 Aug 2026), as of 27 Nov 2026.
Where is it?
In Kokarale, Khatav, Satara, Maharashtra.
How big is it?
It has a stated cost of ₹72 lakh and a site of 4.9 acres.
When was it filed?
The application was filed on 9 Jul 2026.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 11 Aug 2026 |
| Application filed | 9 Jul 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Vishwanath Yadu Nalwade |
| Land area | 4.9 acres (2 ha) |
| Project cost | ₹72 lakh |
| Village / locality | Kokarale |
| Taluk / tehsil | Khatav |
| District | Satara |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-12257 |
In context
127 applications in Satara since January 2022 are in the same category (Mining): 100 approved, 9 filed or under review, and 18 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 4.9 acres, this one is larger than 65% of them.
No other mining lease on record has applied within 5 km of this site.
Where it is
Kokarale, Khatav, Satara, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of Forest Land at Proposed Location No.07 of Construction of 132KV… — lapsed, 5 km away
- Proposal of diversion of forest land at proposed Loc.No.07 of construction of… — in-principle approval, conditions pending, 5 km away
- Diversion of Forest Land for Construction of Existing Kacha Road to Metal/Tar… — in-principle approval, conditions pending, 5.3 km away
- Environmental Clearance for the Stone Quarry of Shri. Amit Ravindra Ithape &… — environmental approval granted, 6 km away
- Shri. Jitendra Bajirao Pawar — environmental approval granted, 6.2 km away
- Environmental Clearance for the Basalt stone quarry of Shri. Sagar Hanmant… — environmental approval granted, 7.4 km away
- Diversion of Forest Land for Laying Optical Fiber Cable Within Row of the… — lapsed, 9.5 km away
- Diversion of Forest Land for Laying Optical Fiber Cable With in Row of the… — in-principle approval, conditions pending, 9.7 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.